3.3.3 Sampling and In Situ Testing

Deciding where, how deep and how many borings and tests a site needs, and writing it so a driller can price it.
Author: Daniel P. Colwell
3.3.3 Sampling and In Situ Testing
Table 3.3-4. Sampling and field tests
MethodUseSpecification notes
Standard Penetration Test (SPT)All soils; strength and density correlations5-ft intervals as a default; continuous in the upper 10 ft or where conditions change; record hammer type and efficiency
Shelby (thin-wall) tubesSoft to stiff clay and silt; consolidation and strength tests3-in. diameter; two per boring where soft clay is found; from an offset boring if needed; sealed and kept upright
Rock coringRock quality, strength, joints, voidsNQ (about 2 in.) core; RQD and recovery; coring contingency where refusal depth is uncertain
Dynamic cone penetrometer (DCP)Pavement subgrade strength; CBR correlationTo 5 ft beside pavement borings; usually covered by the driller's day rate
Pocket penetrometer and torvaneField strength of cohesive samplesEvery cohesive SPT and tube end
Bulk samplesProctor, CBR, resilient modulusAbout 50 lb per sample from the subgrade zone
Photo-ionization detector (PID)Screening in fill, slag and odor areasEvery sample in fill; drum cuttings if readings or odors indicate impacted material
Hand-auger probesSoft-soil depth, ditch conditionsBetween borings; cheap and fast where access is poor
Borehole drilling and sampling. The sampling plan is part of the drilling scope and must be written into the RFP so the driller brings the right tools.
Figure 3.3-4. Borehole drilling and sampling. The sampling plan is part of the drilling scope and must be written into the RFP so the driller brings the right tools.