Lay borings out on the map file from the desktop study (Chapter 3.2), on the features that control design, and away from utilities and property lines. Name them by purpose and number them in one direction along the line (for example west to east) so that field staff, the driller and the report use the same order. Use new prefixes that cannot be confused with legacy borings at the same site.
| Feature | Typical layout | Source |
|---|---|---|
| Embankment or cut slope | Borings at the shoulder or crest and at the toe; 80 to 165 ft apart at critical areas, wider in uniform ground; a railroad's minimum is a three-boring series about every quarter mile | Look, Table 1.8; a Class I railroad's public projects requirements |
| Track subgrade (siding, new main) | One boring every 500 ft in strong soil, 200 ft in medium and 100 ft in weak soil, plus at cuts, fills and culverts; hand-auger or DCP probes between | Li and others (2016) |
| Light towers, signals, bridges | One boring per foundation; at each bridge support | Look, Table 1.8 |
| Pavement and yards | Grid, commonly 300 to 500 ft; denser in heavy-load zones; check grid points against soil map units | Practice |
| Culverts | Under 66 ft: one boring; 66 to 130 ft: one at each end; longer: each end and every 66 ft | Look, Table 1.8 |
Section 3.9.5.3 gives the full criteria, the sources and the planner calculator.
A grid laid on a large wet parcel should be checked against the soil map units before it is priced. On one 123-acre marsh parcel a 500 x 500 ft grid gave 28 borings, 17 in a loamy fill unit and 11 in an undrained clayey unit along the edges; the soft clay unit became the critical case for settlement, and the earlier option of one boring per 50,000 sq ft was dropped as too dense for the question being asked.