Table 3.3-5. Railroad-specific constraints on drilling| Constraint | What to plan |
|---|
| Track protection and flagging | Request flagging through the railroad early; flagging crews often start their week on Tuesday; budget train standby (3.5 hours per day was the average on one line) |
| Fouling zone | No drilling within the fouling distance of track without protection; plan locations off the ballast shoulder where possible |
| Safety training and badging | Railroad contractor safety training and badges for every person on site, including the driller |
| Utilities | Public one-call ticket (by the driller); railroad signal and communication lines located by the railroad; 25-ft clearance from valuation-map utilities |
| Insurance | Driller's insurance to meet the railroad agreement, naming the railroad and the consultant; a rider if the policy excludes work within 50 ft of track |
| Access | Drive on the right-of-way, never on ballast; separate setups for distant reaches (Chapter 3.6) |
| Property | Confirm the right-of-way width at each boring; right-of-entry from neighbors if a boring plots outside it |