3.3.0 Objectives of the Exploration

Deciding where, how deep and how many borings and tests a site needs, and writing it so a driller can price it.
Author: Daniel P. Colwell
3.3.0 Objectives of the Exploration

Every boring needs a stated purpose. If the purpose cannot be written in one line, the boring is either in the wrong place or not needed. Typical purposes on railroad work are: the foundation soils and depth to rock under the toe of a fill that is being steepened; the bearing stratum for a light-tower or signal foundation; the subgrade for heavy-duty pavement; the soft-soil depth for undercut limits; and conditions below a proposed ditch grade.

Table 3.3-1. Matching the exploration to the question
QuestionExploration that answers it
Will a steepened 1.5H:1V fill be stable?Borings at the toe of the new slope to rock or below the critical slip surface; Shelby tubes in soft clay for strength; rock core where refusal is shallow
What will carry a high-mast light tower?One boring per tower to below the expected shaft tip (35 ft in one recent program); SPT at 5-ft intervals
What subgrade will heavy pavement sit on?Shallow borings on a grid (10 ft) with dynamic cone penetrometer (DCP) testing to 5 ft; bulk samples for Proctor and CBR
How deep is the soft soil to be undercut?Hand-auger probes between borings
What is below a new ditch grade?Short borings or hand augers to below the proposed invert (6 ft in one recent program)
What is the groundwater regime?Water at drilling, completion and 24 hours; observation wells or piezometers where seepage controls the design
The parts of a geotechnical investigation. The drilling scope is the field portion, but it is written backward from the analyses the report must support.
Figure 3.3-1. The parts of a geotechnical investigation. The drilling scope is the field portion, but it is written backward from the analyses the report must support.