3.3.4 Groundwater Observation and Instrumentation

Deciding where, how deep and how many borings and tests a site needs, and writing it so a driller can price it.
Author: Daniel P. Colwell
3.3.4 Groundwater Observation and Instrumentation

Record groundwater at first encounter, at completion and, where it matters, after 24 hours. On soft-ground and slope projects a 24-hour reading is worth the short return trip. Where seepage or pore pressure controls design (slopes, levee-like fills, culverts), add observation wells or vibrating-wire piezometers and leave them in place; on unstable slopes add an inclinometer at the critical section (Chapter 5.3).

Grout every boring. Backfill borings full depth with cement-bentonite grout near track, in fills over soft ground and wherever groundwater may be impacted. Cuttings alone can leave a soft column or a vertical drain under the track.