3.3.8 Laboratory Program, Quantities and Contingencies

Deciding where, how deep and how many borings and tests a site needs, and writing it so a driller can price it.
Author: Daniel P. Colwell
3.3.8 Laboratory Program, Quantities and Contingencies

Estimate the laboratory program from the analyses: index tests on most samples, strength and consolidation where the analyses need them, compaction and CBR for pavement, and corrosion tests on slag and cinder fill or where structures are buried. Lab quantities are estimates; the tests run are chosen after the logs are reviewed.

Table 3.3-9. Example laboratory quantities for a 10-boring slope program
TestQuantityPurpose
Moisture content55All samples
Atterberg limits7Classification, strength correlations
Percent finer than No. 2007Classification
Organic content2Where organics are found
Shelby tube extrusion16Logging and specimen selection
Unconfined compression4Undrained strength
Consolidation1 to 2Settlement of soft fat clay
CU triaxial or direct shear2Drained strength for slope stability
Rock unconfined compressionAs coredRock strength
Table 3.3-10. Contingencies to carry
ItemTypical allowanceWhy
Train standbyHours per day from past work on the lineLargest variable cost on busy lines
Refusal and offsetsHalf a day where cemented slag, cobbles or shallow rock are expectedMoves and re-drills
Rock coring5 ft at selected borings, plus a total contingencyRock depth uncertain
Separate setupsOne mobilization per distant reachReaches miles apart need a new setup
Mats and clearingFrom the reconnaissance (Chapter 3.6)Wet or wooded access