Estimate the laboratory program from the analyses: index tests on most samples, strength and consolidation where the analyses need them, compaction and CBR for pavement, and corrosion tests on slag and cinder fill or where structures are buried. Lab quantities are estimates; the tests run are chosen after the logs are reviewed.
Table 3.3-9. Example laboratory quantities for a 10-boring slope program| Test | Quantity | Purpose |
|---|
| Moisture content | 55 | All samples |
| Atterberg limits | 7 | Classification, strength correlations |
| Percent finer than No. 200 | 7 | Classification |
| Organic content | 2 | Where organics are found |
| Shelby tube extrusion | 16 | Logging and specimen selection |
| Unconfined compression | 4 | Undrained strength |
| Consolidation | 1 to 2 | Settlement of soft fat clay |
| CU triaxial or direct shear | 2 | Drained strength for slope stability |
| Rock unconfined compression | As cored | Rock strength |
Table 3.3-10. Contingencies to carry| Item | Typical allowance | Why |
|---|
| Train standby | Hours per day from past work on the line | Largest variable cost on busy lines |
| Refusal and offsets | Half a day where cemented slag, cobbles or shallow rock are expected | Moves and re-drills |
| Rock coring | 5 ft at selected borings, plus a total contingency | Rock depth uncertain |
| Separate setups | One mobilization per distant reach | Reaches miles apart need a new setup |
| Mats and clearing | From the reconnaissance (Chapter 3.6) | Wet or wooded access |