Chapter 3.10 — Mining and Man-Made Hazards

Abandoned mines, buried structures, utilities and old works: hazards that people put in the ground, and how to find them before they find the project.
Author: Daniel P. Colwell

Not every ground hazard is natural. Coal and mineral mining has left voids under thousands of miles of railroad; pipelines and utilities cross the corridor at frequent intervals; and a century of railroad construction has left buried trestles, culverts, foundations and fills. This chapter covers how mine subsidence happens, how to screen for it, and how to find and manage buried man-made obstructions during the risk management phase.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
3.10.0 Purpose and Overview

Man-made hazards differ from natural ones in one useful way: they usually leave records. Mine maps, permits, utility records, railroad valuation maps and construction drawings can locate most of them before any drilling. The risk management task is to find and read those records, then confirm the important hazards in the field.

3.10.1 Mine Subsidence Mechanisms
Table 3.10-1. Types of mine subsidence
TypeMining methodSurface effectTiming
Sinkhole (pit) subsidenceRoom-and-pillar at shallow depthAbrupt pit, typically 5 to 40 ft across, from roof collapse migrating up (chimneying)Decades after mining; often triggered by water
Trough (sag) subsidenceRoom-and-pillar pillar failure; longwallBroad, shallow basin; tension cracks at edges, compression at centerLongwall: during and within months of mining; pillar failure: any time
Shaft and adit collapseAnyPit at the old openingAny time; often hidden by fill
Surface mine highwall and spoilStrip and open-pitSettlement of spoil; instability of old highwallsSpoil settles for decades
Profile view of a site remediated using Bulk Infill Grouting
Photo 3.10.1-1. Profile view of site remediated using Bulk Infill Grouting. From Ryan (1983), courtesy of GeoCon®.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Two excavators working in a deep rock-walled excavation pit with standing water, during a mine subsidence remediation project
Photo 3.10.1-2. Excavation during an abandoned underground mine subsidence remediation, Jackson County State Route 32. From Ohio Department of Transportation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Wide excavated area with heavy equipment and tire tracks during backfilling operations at a mine subsidence remediation site
Photo 3.10.1-3. Replacement (backfilling) during an abandoned underground mine subsidence remediation, Jackson County State Route 32. From Ohio Department of Transportation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Chimneying (void migration) stops when the collapsed debris, which occupies more volume than the intact rock (bulking), fills the void. A simple estimate of the maximum height of migration is:

Hmax ≈ m / (k − 1)(Eq. 3.10-1)
m = mined height (seam thickness); k = bulking factor of the caved rock, typically 1.2 to 1.5. Competent rock layers in the roof can arrest migration below this height.

A widely used screening rule is that sinkhole subsidence is possible where the cover over room-and-pillar workings is less than about 10 times the mined height, and unlikely where it exceeds about 20 times, unless the overburden is weak or water is involved. These ratios are guides for screening, not design values.

3.10.2 Screening for Mining
  • State mine-map repositories and abandoned mine land inventories; historic topographic maps showing mine symbols, tipples, spoil and openings.
  • Coal seam depth and thickness from geologic maps and nearby well and boring logs.
  • LiDAR for subsidence pits, strip-mine benches, spoil piles and filled openings.
  • Railroad records: spurs to tipples, mine-support agreements, repeated maintenance at the same locations.
  • Field reconnaissance: pits, cracks, ponding in new depressions, acid mine drainage (orange staining) at the toe of embankments.

Where screening shows mined seams within roughly 20 times their thickness of the surface, drill to below the seam with continuous coring, logging voids, rubble and water. Mine voids often hold water under pressure; plan for it. Treatment options include grouting the voids (low-mobility grout to form barriers, then flowable fill), excavating and backfilling shallow workings, and bridging. Grouting is covered in Chapter 7.2.

3.10.3 Buried Railroad Works

Older lines carry a buried record of their own construction: timber trestles filled in place, stone and timber box culverts extended and abandoned, old bridge abutments and piers left when lines were relocated, coal and water facilities, and fills over old roadbeds. Timber left in fills decays, leaving voids that can produce sinkholes a century later. Old culverts that were abandoned but not plugged continue to carry water and erode the fill around them.

  • Compare current alignment with valuation maps, historic aerial photographs and old track charts to find trestle and culvert locations.
  • Ask maintenance staff about recurring soft spots and sinkholes; they often know where old timber is.
  • Use GPR and probing along the embankment where trestles are suspected; confirm with test pits.
  • Treat buried timber as a void in design: remove where practical, or grout the zone.
3.10.4 Utilities and Pipelines

Utilities cross railroad corridors frequently and lie along many of them: fiber optic cable, signal and communication lines, power, water and sewer, and oil and gas pipelines. They are both a hazard to the work (strikes during drilling) and a potential trigger (leaking water and sewer lines wash out embankments; a pipeline failure is a severe consequence).

  • Call the one-call center before any drilling, and also request railroad signal and communication locates, which may not be covered by one-call.
  • Clear the top 5 to 10 ft of every boring by hand or vacuum excavation where utilities are possible.
  • Keep explorations outside pipeline easements unless the operator approves and attends.
  • Record utility locations in the KMZ and on the boring location plan.

Drilling scope and safety are described in Chapter 3.3; pipeline crossings have an analysis app in Section 6.0.

3.10.5 Other Man-Made Hazards
Table 3.10-2. Other man-made hazards
HazardWhere foundConcern
Quarries and pitsBeside lines that hauled aggregateSteep faces, backfilled pits with loose fill, dewatering that triggers karst collapse
Landfills and dumpsLow ground near townsSettlement, gas, leachate, debris
Wells (oil, gas, water, brine)Oil fields, salt and potash areasAbandoned well casings; brine dissolution of salt (Chapter 2.11)
Dredge and hydraulic fillsWaterfronts, port areasLoose, liquefiable sands; soft clays
Dams and leveesFloodplainsSeepage, failure flooding consequence
Contaminated groundFueling sites, yards, industrySee Chapter 5.4
3.10.6 Risk Rating

Mining and man-made hazards feed the same 1-to-5 rating used for natural hazards (Chapter 3.8). For mining, frequency is driven by cover ratio and evidence of past subsidence; severity by the size of possible pits and the track's speed and traffic. Buried timber and abandoned culverts rate high when the embankment shows settlement, sinkholes or seepage.

3.10.7 Worked Example
The example uses a generic site and is not taken from any client project. It follows the five-part format.
Example 3.10-1: Screening Abandoned Room-and-Pillar Workings Under an Embankment

A state mine map shows room-and-pillar workings in a 6-ft coal seam below a section of track. A boring near the track found the seam at 45 ft depth, with shale roof rock. A shallow pit appeared in a field 300 ft away last year.

Given

VariableValueDescription
m6 ftMined height (seam thickness)
C45 ftDepth of cover over the workings
k1.3Bulking factor assumed for caved shale
Screening ratiosC/m < 10: sinkhole subsidence possible; > 20: unlikelySection 3.10.1

Required

  • Maximum height of void migration
  • Cover ratio and screening result
  • Whether further investigation is needed

Equations

  1. Eq. 3.10-1: Hmax = m/(k − 1) — maximum chimney height
  2. Eq. 2: C/m — cover ratio

Steps

Step 1 · Void migration height
Hmax = 6 / (1.3 − 1) = 6 / 0.3
Hmax ≈ 20 ft
Spot check: Each foot of void needs about 3.3 ft of caved rock to fill it at k = 1.3: 6 × 3.3 = 20 ft.
↓
Step 2 · Remaining cover
45 − 20
25 ft of cover above the highest likely chimney
Spot check: Positive, so a chimney alone would not reach the surface at k = 1.3.
↓
Step 3 · Cover ratio
C/m = 45 / 6
7.5 < 10: sinkhole subsidence possible
Spot check: Ratio and observed pit nearby both point to susceptibility.
↓
Solution
The simple bulking estimate gives a chimney height of about 20 ft, but the cover ratio of 7.5 is below the screening limit of 10 and a pit has formed nearby. The section is susceptible to sinkhole subsidence and needs investigation.

Solution

The simple bulking estimate gives a chimney height of about 20 ft, but the cover ratio of 7.5 is below the screening limit of 10 and a pit has formed nearby. The section is susceptible to sinkhole subsidence and needs investigation.

The two screens give different signals, and that is common. The bulking estimate assumes the caved rock fills the void evenly; in practice water can carry debris away into the mine, and weak shale may bulk less than assumed, so chimneys can go higher. The nearby pit is direct evidence that they do here. The cover ratio, which is calibrated on such observations, governs.

Next steps: obtain the mine map at the best available scale and overlay it in the KMZ, drill and core to below the seam at several points under the track, and if open voids or rubble are found, plan a grout program to fill the workings under and beside the track. Until then the section should carry a risk rating of at least 4 and be added to the inspection list after heavy rain.

3.10.8 Cross-References

Related chapters in this manual:

Related ICE Manual chapters are listed in the Further Reading box at the top of this chapter and in Appendix G.

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 3.10.1-1 — Profile view of site remediated using Bulk Infill Grouting. From Ryan (1983), courtesy of GeoCon®. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  2. Photo 3.10.1-2 — Excavation during an abandoned underground mine subsidence remediation, Jackson County State Route 32. From Ohio Department of Transportation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  3. Photo 3.10.1-3 — Replacement (backfilling) during an abandoned underground mine subsidence remediation, Jackson County State Route 32. From Ohio Department of Transportation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.