Soluble rocks underlie a large share of the eastern and central United States, and gypsum and salt are common in the plains and the Southwest. Dissolution opens voids in the rock and the soil above ravels down into them, forming cover-collapse sinkholes that can appear in hours with little warning. This chapter describes the sinkhole types, how to find karst features, why borings alone rarely find them, how to rate the risk, and how to treat them under track.
Karst is the landscape that forms on soluble rock. Its features include sinkholes, sinking streams, springs, caves, pinnacled rock surfaces and soil-filled slots. For railroads, karst matters because it causes sudden, local loss of support under track, often after a change in water: a new culvert outfall, a broken water main, a ditch that now discharges into a sinkhole, drawdown from a quarry or well field, or an intense storm.
The governing difficulty is that karst features are small compared with the spacing of any practical boring program, and the rock surface can vary by tens of feet across a few feet horizontally. A site can be explored with a dozen borings that miss every void. The investigation therefore relies on desktop study and geophysics to find anomalies, and on borings to confirm them.
| Rock | Relative solubility | Engineering significance |
|---|---|---|
| Limestone, dolomite, marble (carbonates) | Slow; features form over thousands of years | Voids and sinkholes form mainly by soil raveling into existing openings; rock voids change little in a structure's life |
| Gypsum and anhydrite | Roughly 100 times faster than limestone | New voids can form within a structure's life where flowing water reaches the rock; anhydrite swells as it hydrates |
| Rock salt (halite) | Very fast | Rapid subsidence where fresh water reaches salt, often from wells, mines or brine extraction |
Gypsum and salt are the dangerous cases because dissolution can be fast enough to matter during the service life of an embankment or bridge. A drainage change that sends fresh water into gypsum-bearing ground should be treated as a potential new trigger.
| Type | Mechanism | Speed | Railroad significance |
|---|---|---|---|
| Solution (dissolution) | Gradual lowering of the rock surface where water concentrates | Very slow | Shallow depressions; drainage problems |
| Cover-subsidence | Sandy cover gradually ravels into openings, forming a bowl | Slow, months to years | Progressive settlement; detectable by survey |
| Cover-collapse | Clayey cover arches over a growing void until the arch fails | Sudden, minutes to hours | The main hazard: abrupt loss of support under track |
| Caprock (bedrock) collapse | Roof of a cave collapses | Sudden | Rare at shallow depth; important for bridges and deep cuts |
| Buried (filled) sinkhole | An old sinkhole filled with soft soil | Static until loaded or wetted | Differential settlement and soft pockets; often found during construction |
Most sinkholes that affect railroads are cover-collapse or cover-subsidence sinkholes induced by concentrated water: the soil is washed down into the rock openings from above (raveling), or a falling water table removes buoyant support from the soil arch. Both are driven by human changes to drainage far more often than by natural processes alone.
These sources are free and fast, and they should be finished before any geophysics or drilling is scoped (Chapter 3.2).
Because the features are small, the chance that a boring grid hits a given void is low. For a circular void of diameter D and a square boring grid of spacing S, with D smaller than S:
A 10-ft void under a 50-ft grid has about a 3% chance of being hit. This is why geophysics comes first. Electrical resistivity imaging (ERI) and multichannel analysis of surface waves (MASW) are the most widely used methods for mapping the rock surface and soil-filled zones; microgravity finds air-filled voids; ground-penetrating radar works in sandy cover but not in clay. Borings then target the anomalies and a few control points.
| Method | Finds | Limitations |
|---|---|---|
| Electrical resistivity imaging | Rock surface, clay-filled slots, wet raveled zones | Resolution falls with depth; needs ground contact |
| MASW / seismic | Soft zones and rock surface | Lower lateral resolution |
| Microgravity | Air-filled voids | Slow; sensitive to terrain and nearby mass |
| Ground-penetrating radar | Shallow voids and raveled zones in sandy cover | Little penetration in clay |
| Borings with rock coring | Confirms rock, voids, infill; loss of circulation and rod drops are key observations | Point data; low chance of hitting voids |
| Probe holes (air track) | Rapid check of rock surface and voids on a tight grid | No samples |
In borings, log rod drops, loss of drilling fluid, soft or very soft soil just above rock and sudden changes in rock depth. These observations are often more valuable than the samples themselves (Chapter 4.1).
A karst risk rating combines the geology (is the rock soluble, and how deep), evidence of activity (existing sinkholes, maintenance history) and triggers (concentrated water, drawdown).
| Rating | Geology and evidence | Triggers |
|---|---|---|
| 1 Very low | Non-soluble rock, or soluble rock under more than 100 ft of cover | None |
| 2 Low | Soluble rock mapped; no sinkholes within 1/4 mile | Normal drainage |
| 3 Moderate | Sinkholes mapped within 1/4 mile; pinnacled rock in borings | Culverts or ditches discharging toward karst |
| 4 High | Sinkholes within 500 ft; past subsidence at or near the track | Concentrated discharge into ground; nearby pumping or quarrying |
| 5 Severe | Active depression or void under track; gypsum or salt with fresh water reaching it | Ongoing; recent storm or water main break |
Karst is a natural candidate for the live risk rating described in Chapter 3.8: rainfall intensity and water levels in nearby wells are measurable triggers that raise the likelihood of collapse for a known susceptible site.
| Method | Description | Use |
|---|---|---|
| Drainage control | Redirect concentrated water away from karst; line ditches; avoid discharging culverts into sinkholes | Always; often the most effective measure |
| Inverted filter repair | Excavate to rock throat, plug with large stone and concrete, then graded filter and compacted clay cap | Individual sinkholes accessible from the surface |
| Compaction grouting | Low-slump grout injected to densify raveled soil and fill voids above rock | Under operating track; limits ground loss |
| Cap (cavity) grouting | Flowable grout injected at the rock surface to seal the throats feeding raveling | Large areas of pinnacled rock |
| Geosynthetic bridging | High-strength geogrid or geotextile layer under the track to span a future void and give warning by sagging | Long lengths where voids cannot all be found |
| Structural bridging | Slab or short span over a known void | Severe, localized cases |





Grouting methods are described in Chapter 7.2. Grout volumes in karst are notoriously hard to predict; a refusal criterion (pressure and take) and a contingency in the estimate are essential.
A siding is to be built over limestone with mapped sinkholes nearby. The first proposal is a 50-ft boring grid. Resistivity later shows a raveled zone 40 ft long and 30 ft wide extending 12 ft above rock, and borings in the zone indicate about 15% voids and very soft soil that will take grout.
| Variable | Value | Description |
|---|---|---|
| D | 10 ft | Typical void (throat) diameter assumed |
| S | 50 ft, then 25 ft | Boring grid spacings considered |
| L × B × T | 40 ft × 30 ft × 12 ft | Raveled zone from resistivity and borings |
| nv | 0.15 | Estimated void and very soft fraction to be filled |
| k | 1.3 | Grout waste and travel factor |
A 50-ft grid has only about a 3% chance of hitting a single 10-ft void (13% at 25 ft). The raveled zone found by resistivity needs on the order of 100 cy of grout, which should be carried with a contingency.
Even a tight boring grid is a poor tool for finding karst voids; four times the borings raised the detection chance only from 3% to 13%. Geophysics found the raveled zone, and the borings were then placed where they could confirm it. That sequence (desktop study, geophysics, targeted borings) is the efficient way to investigate karst.
Grout takes in karst routinely exceed estimates because grout follows openings outside the target zone. Specify a refusal criterion, start with primary holes on a wide spacing and close in with secondary and tertiary holes, and carry a contingency of 50 to 100% on grout quantity in the estimate (Chapter 3.7).
Related chapters in this manual:
Related ICE Manual chapters are listed in the Further Reading box at the top of this chapter and in Appendix G.
The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.