Chapter 2.10 — Non-Engineered Fills: Old Embankments, Waste and Made Ground

Most of the railroad network sits on fill placed before modern compaction control. This chapter covers how to characterize it and how it behaves.
Author: Daniel P. Colwell

Much of the North American railroad network was built between about 1850 and 1920, when embankments were end-dumped from cars or wagons, sidehill fills were cast over the slope, and whatever came out of the nearest cut went into the fill. Ballast, cinders, ties and debris were added on top for a century after. These are non-engineered fills: built without specified materials, lift thickness or density control. They are usually serviceable because they have had a century to settle, but they are variable, they creep, and they respond badly to new load, new water and new excavation. This chapter covers their types, investigation, properties, settlement and design.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
2.10.0 Purpose and Overview

A fill is engineered when its material, placement and compaction were specified and checked. Anything else is non-engineered, whatever its age or appearance. The distinction matters because engineered fill can be designed with predictable parameters, while non-engineered fill has to be investigated as a variable natural deposit, often more variable than the ground beneath it.

On a railroad, non-engineered fill includes the original embankments, the accumulated ballast and cinder section above them, widenings and siding fills added over the years, spoil from ditch cleaning cast on the shoulders, and fills placed over old trestles and timber culverts. Each has a different history and needs to be logged as its own unit.

2.10.1 Types of Fill on Railroad Corridors
Table 2.10-1. Fill types commonly met on railroad corridors
Fill typeDescriptionTypical concerns
End-dumped embankmentOriginal earth fill tipped from the end of the grade, no liftsLoose zones, segregation (coarse at toe), creep, internal shear surfaces
Sidehill cast fillMaterial pushed or cast down a slope from a benchSteep, loose outer shell on original slope; slides on the old ground surface
Trestle fill-inTimber trestle buried in fill, often with timbers left in placeDecaying timber voids; sinkholes years later
Ballast and cinder sectionFouled ballast, cinders, slag and ballast pockets built up over a centuryWater-holding pockets, fouling, frost, contamination (Chapter 5.4)
Widening fillLater fill placed beside the original embankmentDifferential settlement against the older, settled fill; poor bond on slope
Spoil and wasteDitch spoil, dredge spoil, demolition debris, mine wasteOrganics, loose structure, chemistry
Industrial wasteSlag, fly ash, foundry sand, mine tailingsExpansive slags, sulfates, leachate
Yellow resonant breaker machine rubblizing an existing pavement surface on a highway, with workers in orange safety vests alongside
Photo 2.10.1-1. Rubblization using RMI Resonant Breaker. Photograph courtesy of Resonant Machines, Inc., 2005.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Aerial photograph of the cable-stayed Leonard P. Zakim Bunker Hill Bridge in Boston, part of the Central Artery/Tunnel project, spanning the Charles River with
Photo 2.10.1-2. Storrow Drive Connector, Boston Central Artery/Tunnel Project, Massachusetts. Photograph from EPA-530-K-05-002 (2005), courtesy of U.S. Environmental Protection Agency.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Excavator sorting construction and demolition waste inside an industrial processing facility
Photo 2.10.1-3. Construction and demolition wastes to be processed at the Remex processing plant in Germany. From Schimmoller et al. (2000).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Close-up of a pipe in a narrow trench being backfilled with flowable fill
Photo 2.10.1-4. Flowable fill used to backfill very narrow trenches. From ACCA (2003).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Front loader spreading shredded tire chips at a highway embankment construction site
Photo 2.10.1-5. Shredded tires being used as fill for highway embankment construction. From Stevens (2007).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Old company valuation maps and track charts, aerial photographs and historical topographic maps often show where trestles were filled, where the line was relocated and where widenings were added. These records belong in the desktop study (Chapter 3.2).

2.10.2 Investigating Fills

Fill variability is the governing problem, so investigation should aim to define the range of conditions rather than a single average profile.

  • Log fill and natural ground as separate units, and record the fill-to-native contact; the old ground surface is often a weak organic layer and a preferred slip surface.
  • Use test pits where access allows: they show debris, voids, timbers and the fill structure that a 2-in. split spoon cannot.
  • Supplement borings with continuous methods along the embankment, such as dynamic cone penetrometer soundings, CPT or ground-penetrating radar for the ballast and subballast section (Chapter 5.1).
  • Expect SPT values to be erratic. A single high blow count on a cobble or tie can mask a loose zone; record and discuss the scatter rather than averaging it away.
  • Sample for organic content, and for chemistry where cinders, slag or industrial waste are present (sulfates and leachable metals; see Chapters 2.12 and 5.4).
  • Install piezometers where the fill may hold perched water; old embankments frequently trap water above a clay core or the original ground surface.

Spacing of explorations in fill should be closer than in natural ground of the same apparent uniformity. Where only a few borings are possible, put them where the history says conditions change: at old trestle locations, culverts, widenings and the ends of cuts.

2.10.3 Engineering Properties
Table 2.10-2. Typical behavior of non-engineered fills (indicative only; verify by testing)
FillRelative density / consistencyCreep coefficient α (% per log cycle)Notes
Well-graded granular, oldMedium dense0.2 to 0.5Settles little once aged
Sandy and silty fill, end-dumpedLoose to medium dense0.5 to 1.0Collapse-prone if dry (Chapter 2.9)
Clay fill, end-dumpedSoft to stiff, lumpy1.0 to 2.0Voids between clods close on wetting
Mixed fill with organics or debrisVariable2.0 to 5.0 or moreDecay continues to cause settlement
Cinders and slagLoose0.5 to 1.5Some slags expand; check chemistry

Strength parameters for fill should be chosen from tests on the fill itself, conservatively for loose and mixed zones. Do not assume that an old embankment that has stood for a century has a high factor of safety: many stand at factors close to 1.0 and fail when ditches are cleaned out at the toe, when water levels rise, or when the slope is loaded.

2.10.4 Settlement of Fills

An old fill continues to settle under its own weight at a rate that falls with the logarithm of time since placement. This self-weight creep is small for century-old fills but large for new ones, which is why widenings settle against the original embankment.

S = α H log10(t2 / t1)(Eq. 2.10-1)
α = creep compression per log cycle of time (as a decimal); H = fill thickness; t1, t2 = times since the end of filling.

New load on old fill (a second main track, a heavier embankment section) is analyzed with ordinary settlement methods using parameters from the fill. Wetting of a fill placed dry can add collapse settlement (Chapter 2.9), and decay of buried timber or organics adds settlement that no time-based equation predicts; these are best found by investigation and handled by removal.

2.10.5 Design Considerations
  • Widenings and second tracks: bench into the old embankment slope, remove loose outer shell and vegetation, and compact the new fill in lifts. Expect the new fill to settle more than the old; consider surcharging or lightweight fill where the difference matters to track geometry.
  • Culverts and buried structures: look for old timber boxes and trestle bents. Voids left by decay are a common cause of sudden sinkholes in old embankments.
  • Slope stability: model the fill and the old ground surface separately; check failure along the original ground contact.
  • Drainage: perched water in old fill drives both instability and track pumping. Edge drains and toe drains are often more effective than strengthening.
  • Excavation: trenches and test pits in fill stand poorly and can encounter debris; plan shoring and treat the fill as a Type C soil for trench safety unless testing shows otherwise.

Remedial options for fills, including grouting of voids and replacement, are covered in Chapter 7.2 and Chapter 7.4.

2.10.6 Worked Example
The example uses a generic site and is not taken from any client project. It follows the five-part format.
Example 2.10-1: Creep Settlement of an Old Embankment and a New Widening

A second main track is to be added beside a 25-ft-high clay embankment that was end-dumped in 1905. The widening adds 10 ft of new, compacted clay fill against the old slope. The question is how much each part will settle by self-weight creep over the next 20 years, since the difference shows up as cross-level change between the two tracks.

Given

VariableValueDescription
Hold25 ftOld embankment height
t (old)121 yr now (2026); 141 yr in 20 yearsAge since end of filling
Hnew10 ftAverage new fill thickness
t (new)1 yr to 21 yrTime window measured from end of filling; first year handled by construction
α1.0% per log cycle (0.010)Clay fill (Table 2.10-2); same value used for both for comparison

Required

  • Creep settlement of the old embankment over the next 20 years
  • Creep settlement of the new fill from year 1 to year 21
  • Differential settlement between them

Equations

  1. Eq. 2.10-1: S = α H log10(t2/t1) — creep of fill under self-weight

Steps

Step 1 · Old embankment
S = 0.010 × (25 × 12 in) × log(141/121) = 0.010 × 300 × 0.066
Sold ≈ 0.2 in
Spot check: From 121 to 141 years is far less than one log cycle (0.066), so creep is almost finished.
↓
Step 2 · New widening
S = 0.010 × (10 × 12 in) × log(21/1) = 0.010 × 120 × 1.32
Snew ≈ 1.6 in
Spot check: 1 to 21 years is about 1.3 log cycles, so the new fill settles about 1.3% of its height.
↓
Step 3 · Differential
1.6 − 0.2
ΔS ≈ 1.4 in
Spot check: The new fill settles about eight times as much as the old, though it is less than half as high.
↓
Solution
Over 20 years the old embankment creeps about 0.2 in, the new widening about 1.6 in, a differential of about 1.4 in between the two tracks.

Solution

Over 20 years the old embankment creeps about 0.2 in, the new widening about 1.6 in, a differential of about 1.4 in between the two tracks.

Age is the controlling variable: the old embankment has had a century of creep and has very little left, while the new fill is at the steep part of its log-time curve. That is why widenings settle against the original embankment even when the new fill is well compacted.

Most of the new fill creep happens early: of the 1.6 in, about 0.6 in (more than a third) occurs between years 1 and 3. Placing the new fill a season ahead of track construction, or surcharging it, takes up much of the difference before the track is laid. Benching into the old slope and compacting the new fill near optimum moisture keep the actual creep coefficient near the low end of the range.

2.10.7 Cross-References

Related chapters in this manual:

Related ICE Manual chapters are listed in the Further Reading box at the top of this chapter and in Appendix G.

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 2.10.1-1 — Rubblization using RMI Resonant Breaker. Photograph courtesy of Resonant Machines, Inc., 2005. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  2. Photo 2.10.1-2 — Storrow Drive Connector, Boston Central Artery/Tunnel Project, Massachusetts. Photograph from EPA-530-K-05-002 (2005), courtesy of U.S. Environmental Protection Agency. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  3. Photo 2.10.1-3 — Construction and demolition wastes to be processed at the Remex processing plant in Germany. From Schimmoller et al. (2000). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  4. Photo 2.10.1-4 — Flowable fill used to backfill very narrow trenches. From ACCA (2003). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  5. Photo 2.10.1-5 — Shredded tires being used as fill for highway embankment construction. From Stevens (2007). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.