2.12.4 Slaking and Degradable Mudrocks

Ground chemistry that attacks concrete, heaves stabilized subgrades and turns fresh shale into soil within a few seasons of exposure.
Author: Daniel P. Colwell
2.12.4 Slaking and Degradable Mudrocks

Many shales, mudstones and claystones are rock in the boring and soil a few seasons after the cut is opened. Wetting and drying, unloading and frost break them down along bedding, and the debris accumulates in ditches, fouls ballast and falls on the track. Durability is measured by the slake durability index (ASTM D4644, withdrawn 2025), with the second-cycle value Id2 usually reported.

Table 2.12-3. Slake durability classification (second cycle)
Id2 (%)DurabilityBehavior in cuts and fills
0 to 30Very lowDegrades to soil within months; treat as soil for slopes and fill
31 to 60LowSlakes in a few seasons; flatten cuts or protect faces
61 to 85MediumGradual surface degradation; ditch cleaning
86 to 95HighDurable with normal design
96 to 100Very highDurable

Low-durability mudrocks placed as rockfill break down after placement and cause settlement of the embankment, so they should be compacted in thin lifts as soil. In cuts, design benches and ditches to catch debris, and consider shotcrete or vegetation for faces in very low durability rock. Rock slope stability is covered in Chapter 2.7.