Much of the North American railroad network was built between about 1850 and 1920, when embankments were end-dumped from cars or wagons, sidehill fills were cast over the slope, and whatever came out of the nearest cut went into the fill. Ballast, cinders, ties and debris were added on top for a century after. These are non-engineered fills: built without specified materials, lift thickness or density control. They are usually serviceable because they have had a century to settle, but they are variable, they creep, and they respond badly to new load, new water and new excavation. This chapter covers their types, investigation, properties, settlement and design.
A fill is engineered when its material, placement and compaction were specified and checked. Anything else is non-engineered, whatever its age or appearance. The distinction matters because engineered fill can be designed with predictable parameters, while non-engineered fill has to be investigated as a variable natural deposit, often more variable than the ground beneath it.
On a railroad, non-engineered fill includes the original embankments, the accumulated ballast and cinder section above them, widenings and siding fills added over the years, spoil from ditch cleaning cast on the shoulders, and fills placed over old trestles and timber culverts. Each has a different history and needs to be logged as its own unit.
| Fill type | Description | Typical concerns |
|---|---|---|
| End-dumped embankment | Original earth fill tipped from the end of the grade, no lifts | Loose zones, segregation (coarse at toe), creep, internal shear surfaces |
| Sidehill cast fill | Material pushed or cast down a slope from a bench | Steep, loose outer shell on original slope; slides on the old ground surface |
| Trestle fill-in | Timber trestle buried in fill, often with timbers left in place | Decaying timber voids; sinkholes years later |
| Ballast and cinder section | Fouled ballast, cinders, slag and ballast pockets built up over a century | Water-holding pockets, fouling, frost, contamination (Chapter 5.4) |
| Widening fill | Later fill placed beside the original embankment | Differential settlement against the older, settled fill; poor bond on slope |
| Spoil and waste | Ditch spoil, dredge spoil, demolition debris, mine waste | Organics, loose structure, chemistry |
| Industrial waste | Slag, fly ash, foundry sand, mine tailings | Expansive slags, sulfates, leachate |





Old company valuation maps and track charts, aerial photographs and historical topographic maps often show where trestles were filled, where the line was relocated and where widenings were added. These records belong in the desktop study (Chapter 3.2).
Fill variability is the governing problem, so investigation should aim to define the range of conditions rather than a single average profile.
Spacing of explorations in fill should be closer than in natural ground of the same apparent uniformity. Where only a few borings are possible, put them where the history says conditions change: at old trestle locations, culverts, widenings and the ends of cuts.
| Fill | Relative density / consistency | Creep coefficient α (% per log cycle) | Notes |
|---|---|---|---|
| Well-graded granular, old | Medium dense | 0.2 to 0.5 | Settles little once aged |
| Sandy and silty fill, end-dumped | Loose to medium dense | 0.5 to 1.0 | Collapse-prone if dry (Chapter 2.9) |
| Clay fill, end-dumped | Soft to stiff, lumpy | 1.0 to 2.0 | Voids between clods close on wetting |
| Mixed fill with organics or debris | Variable | 2.0 to 5.0 or more | Decay continues to cause settlement |
| Cinders and slag | Loose | 0.5 to 1.5 | Some slags expand; check chemistry |
Strength parameters for fill should be chosen from tests on the fill itself, conservatively for loose and mixed zones. Do not assume that an old embankment that has stood for a century has a high factor of safety: many stand at factors close to 1.0 and fail when ditches are cleaned out at the toe, when water levels rise, or when the slope is loaded.
An old fill continues to settle under its own weight at a rate that falls with the logarithm of time since placement. This self-weight creep is small for century-old fills but large for new ones, which is why widenings settle against the original embankment.
New load on old fill (a second main track, a heavier embankment section) is analyzed with ordinary settlement methods using parameters from the fill. Wetting of a fill placed dry can add collapse settlement (Chapter 2.9), and decay of buried timber or organics adds settlement that no time-based equation predicts; these are best found by investigation and handled by removal.
Remedial options for fills, including grouting of voids and replacement, are covered in Chapter 7.2 and Chapter 7.4.
A second main track is to be added beside a 25-ft-high clay embankment that was end-dumped in 1905. The widening adds 10 ft of new, compacted clay fill against the old slope. The question is how much each part will settle by self-weight creep over the next 20 years, since the difference shows up as cross-level change between the two tracks.
| Variable | Value | Description |
|---|---|---|
| Hold | 25 ft | Old embankment height |
| t (old) | 121 yr now (2026); 141 yr in 20 years | Age since end of filling |
| Hnew | 10 ft | Average new fill thickness |
| t (new) | 1 yr to 21 yr | Time window measured from end of filling; first year handled by construction |
| α | 1.0% per log cycle (0.010) | Clay fill (Table 2.10-2); same value used for both for comparison |
Over 20 years the old embankment creeps about 0.2 in, the new widening about 1.6 in, a differential of about 1.4 in between the two tracks.
Age is the controlling variable: the old embankment has had a century of creep and has very little left, while the new fill is at the steep part of its log-time curve. That is why widenings settle against the original embankment even when the new fill is well compacted.
Most of the new fill creep happens early: of the 1.6 in, about 0.6 in (more than a third) occurs between years 1 and 3. Placing the new fill a season ahead of track construction, or surcharging it, takes up much of the difference before the track is laid. Benching into the old slope and compacting the new fill near optimum moisture keep the actual creep coefficient near the low end of the range.
Related chapters in this manual: