| Approach | Method | Best use | Limitations |
|---|---|---|---|
| Keep it dry | Repair culverts and joints, line ditches, regrade to drain away from the track, seal tension cracks | Existing track; always the first step | Needs ongoing maintenance |
| Remove and replace | Excavate collapsible soil and recompact at or above optimum moisture | Shallow deposits under new works | Track outage; cost grows fast with depth |
| Pre-wet (prewetting / ponding) | Flood the foundation before building so collapse happens first | New embankments on thick deposits | Slow; uneven wetting; can soften the ground |
| Densify | Dynamic compaction, rapid impact compaction, compaction grouting | Deposits 10 to 30 ft thick | Vibration near operating track |
| Stabilize | Chemical (lime, cement) or permeation grouting | Culvert bedding, bridge approaches | Sulfate check needed (Chapter 2.12) |
| Bypass | Deep foundations through the collapsible zone | Bridges and structures | Downdrag when collapse occurs |
Densification and stabilization methods are described in Chapter 7.2. Whatever is done to the soil, the drainage that started the problem has to be fixed as well.