2.9.6 Railroad Impacts and Risk Rating

Dry, low-density soils that hold their shape until they get wet, then lose volume suddenly under the load they already carry.
Author: Daniel P. Colwell
2.9.6 Railroad Impacts and Risk Rating

Collapse shows up on a railroad as localized sags, twist and cross-level defects at drainage features, cracking and slumping of embankment shoulders, and loss of support under culvert ends and bridge approaches. Because the trigger is water, the frequency side of the risk rating is driven by drainage condition and climate, and the severity side by the collapse index and the thickness of collapsible soil.

Table 2.9-4. Suggested collapse hazard inputs to the 1-to-5 risk rating (Chapter 3.8)
RatingCollapse index / soilWetting exposure
1 Very lowIc < 1%, or soil already near saturationPositive drainage; no ponding
2 LowIc 1 to 2%Minor seasonal ponding away from track
3 ModerateIc 2 to 6% in less than 10 ft of soilCulverts or ditches crossing the collapsible zone
4 HighIc 2 to 6% over more than 10 ft, or 6 to 10%Known leaking culvert, ponding against embankment
5 SevereIc > 10%Active wetting with observed settlement or cracking

These bands are offered as a starting point; they should be calibrated in the risk-ratings workbook alongside the other ground hazards so that a "4" for collapse means the same likelihood of a track defect as a "4" for any other hazard.