3.4.4 Drainage Observations

Planning and carrying out the site visit, and recording what the ground, the drainage and the track are telling you.
Author: Daniel P. Colwell
3.4.4 Drainage Observations

Most of the ground hazards on a railroad are drainage problems first. Walk every culvert inlet and outlet and every ditch that carries water toward or away from the fill.

Table 3.4-5. Drainage indicators
FeatureLook for
Culvert inletsSilt, debris, vegetation or beaver activity reducing the opening; ponding or water marks upstream; headwall condition
Culvert outletsScour holes, undermined headwalls, separated or crushed pipe, piping through the fill
Ditches and swalesStanding water, mud bottoms, cut channels, blocked flow; color and odor of water
Toe of fillWater ponded against the fill; soft, wet ground
Overgrown culvert inlet under a main-line fill. Vegetation and silt reduce the opening, which raises the frequency at which water ponds against the fill (the trigger rating of Section 3.8.18).
Figure 3.4-3. Overgrown culvert inlet under a main-line fill. Vegetation and silt reduce the opening, which raises the frequency at which water ponds against the fill (the trigger rating of Section 3.8.18).
Culvert outlets at the toe of a fill, one with an exposed, separated pipe section. Separated joints let water and fines move through the embankment.
Figure 3.4-4. Culvert outlets at the toe of a fill, one with an exposed, separated pipe section. Separated joints let water and fines move through the embankment.
Record odors. A sewage-type odor at ditches on a filled site can come from a leaking sewer, hydrogen sulfide from organic muck or sulfur-bearing slag, or leachate. Note which ditch, and brief the environmental team before drilling nearby.