3.4.2 Track Observations

Planning and carrying out the site visit, and recording what the ground, the drainage and the track are telling you.
Author: Daniel P. Colwell
3.4.2 Track Observations

The track is the most sensitive instrument on the site. Before walking off the right-of-way, look along the rails from both ends of the site.

Table 3.4-3. Track indicators of ground problems
IndicatorWhat it may mean
Dips in profile, cross-level variation, alignment kinksSubgrade settlement, slope movement or a soft spot over a culvert
Fresh ballast in one location, or ballast built up on the shoulderRepeated surfacing to correct a recurring defect
Mud pumping, fouled ballast, standing water in the cribsPoor drainage and soft subgrade
Narrow or steep shoulder, ballast spilling down the slopeLoss of embankment width; erosion or slope creep
Slow-order signsA defect the railroad is already managing

Ask the railroad for the geometry-car exception history and surfacing records for the segment; whether the same defect comes back between surfacing cycles is the evidence the defect rating of Table 3.8-10 is built on.