3.4.1 Planning the Visit

Go with the desktop study map loaded on a phone or tablet, the proposed boring coordinates, and a short list of questions. Plan the walk so that each boring is visited from the direction the rig will come.

Table 3.4-2. Reconnaissance kit and preparation
ItemNotes
Railroad safety training, badge, PPERequired for everyone on the right-of-way; arrange a flagman or lookout where the walk is within the fouling zone
PermissionCoordinate with the railroad and any landowners whose ground the routes cross
Map file and coordinatesDesktop study KMZ with borings, legacy borings, utilities, parcels, wetlands
Phone or tablet with geotagged cameraCheck that location and compass direction are being recorded
Flagging ribbon, stakes, marking paintOne color for routes, another for borings
Field notebook and worksheetRoute stations; the ground hazard field form where a risk assessment is being made
Hand toolsProbe rod or hand auger for soft ground; tape; clinometer
Time it. A focused visit to ten borings strung along a mile of track can take about an hour and a half. A full access reconnaissance of nineteen off-road borings on a wooded site took three days on foot.