3.4.0 Purpose and Overview

Planning and carrying out the site visit, and recording what the ground, the drainage and the track are telling you.
Author: Daniel P. Colwell
3.4.0 Purpose and Overview

No desktop study survives the first walk of the site unchanged. The reconnaissance confirms or moves the planned borings, finds the way in for the rig, and records the evidence of instability or poor drainage that the maps cannot show. On ground hazard work it is also the field half of the risk rating: what the engineer sees sets the defect rating and confirms the trigger (Chapter 3.8).

Table 3.4-1. What a reconnaissance is for
ObjectiveOutput
Confirm or relocate planned boringsStakes or paint at each boring; relocations recorded with distance and direction
Find and flag accessRibbon-flagged routes from drivable surfaces to each off-road boring
Document vegetation, slopes, ditches, soft ground and obstructionsGeotagged photo log; quantities for clearing and mats (Chapter 3.6)
Identify utilities, property lines and permitsUtility marks, cabinets and conduits photographed; owners along each route
Record instability and drainage evidenceField worksheet blocks for conditions and instabilities (Section 3.8.24)
Talk with the people who know the siteNotes from track forces, yard staff and landowners