No desktop study survives the first walk of the site unchanged. The reconnaissance confirms or moves the planned borings, finds the way in for the rig, and records the evidence of instability or poor drainage that the maps cannot show. On ground hazard work it is also the field half of the risk rating: what the engineer sees sets the defect rating and confirms the trigger (Chapter 3.8).
| Objective | Output |
|---|---|
| Confirm or relocate planned borings | Stakes or paint at each boring; relocations recorded with distance and direction |
| Find and flag access | Ribbon-flagged routes from drivable surfaces to each off-road boring |
| Document vegetation, slopes, ditches, soft ground and obstructions | Geotagged photo log; quantities for clearing and mats (Chapter 3.6) |
| Identify utilities, property lines and permits | Utility marks, cabinets and conduits photographed; owners along each route |
| Record instability and drainage evidence | Field worksheet blocks for conditions and instabilities (Section 3.8.24) |
| Talk with the people who know the site | Notes from track forces, yard staff and landowners |