2.10.6 Worked Example

Most of the railroad network sits on fill placed before modern compaction control. This chapter covers how to characterize it and how it behaves.
Author: Daniel P. Colwell
2.10.6 Worked Example
The example uses a generic site and is not taken from any client project. It follows the five-part format.
Example 2.10-1: Creep Settlement of an Old Embankment and a New Widening

A second main track is to be added beside a 25-ft-high clay embankment that was end-dumped in 1905. The widening adds 10 ft of new, compacted clay fill against the old slope. The question is how much each part will settle by self-weight creep over the next 20 years, since the difference shows up as cross-level change between the two tracks.

Given

VariableValueDescription
Hold25 ftOld embankment height
t (old)121 yr now (2026); 141 yr in 20 yearsAge since end of filling
Hnew10 ftAverage new fill thickness
t (new)1 yr to 21 yrTime window measured from end of filling; first year handled by construction
α1.0% per log cycle (0.010)Clay fill (Table 2.10-2); same value used for both for comparison

Required

  • Creep settlement of the old embankment over the next 20 years
  • Creep settlement of the new fill from year 1 to year 21
  • Differential settlement between them

Equations

  1. Eq. 2.10-1: S = α H log10(t2/t1) — creep of fill under self-weight

Steps

Step 1 · Old embankment
S = 0.010 × (25 × 12 in) × log(141/121) = 0.010 × 300 × 0.066
Sold ≈ 0.2 in
Spot check: From 121 to 141 years is far less than one log cycle (0.066), so creep is almost finished.
↓
Step 2 · New widening
S = 0.010 × (10 × 12 in) × log(21/1) = 0.010 × 120 × 1.32
Snew ≈ 1.6 in
Spot check: 1 to 21 years is about 1.3 log cycles, so the new fill settles about 1.3% of its height.
↓
Step 3 · Differential
1.6 − 0.2
ΔS ≈ 1.4 in
Spot check: The new fill settles about eight times as much as the old, though it is less than half as high.
↓
Solution
Over 20 years the old embankment creeps about 0.2 in, the new widening about 1.6 in, a differential of about 1.4 in between the two tracks.

Solution

Over 20 years the old embankment creeps about 0.2 in, the new widening about 1.6 in, a differential of about 1.4 in between the two tracks.

Age is the controlling variable: the old embankment has had a century of creep and has very little left, while the new fill is at the steep part of its log-time curve. That is why widenings settle against the original embankment even when the new fill is well compacted.

Most of the new fill creep happens early: of the 1.6 in, about 0.6 in (more than a third) occurs between years 1 and 3. Placing the new fill a season ahead of track construction, or surcharging it, takes up much of the difference before the track is laid. Benching into the old slope and compacting the new fill near optimum moisture keep the actual creep coefficient near the low end of the range.