2.10.4 Settlement of Fills

Most of the railroad network sits on fill placed before modern compaction control. This chapter covers how to characterize it and how it behaves.
Author: Daniel P. Colwell
2.10.4 Settlement of Fills

An old fill continues to settle under its own weight at a rate that falls with the logarithm of time since placement. This self-weight creep is small for century-old fills but large for new ones, which is why widenings settle against the original embankment.

S = α H log10(t2 / t1)(Eq. 2.10-1)
α = creep compression per log cycle of time (as a decimal); H = fill thickness; t1, t2 = times since the end of filling.

New load on old fill (a second main track, a heavier embankment section) is analyzed with ordinary settlement methods using parameters from the fill. Wetting of a fill placed dry can add collapse settlement (Chapter 2.9), and decay of buried timber or organics adds settlement that no time-based equation predicts; these are best found by investigation and handled by removal.