Most geotechnical change orders come from a short list of ground risks that were known, at least as possibilities, before the bid: soft subgrade, rock above grade, groundwater, buried obstructions, and the lost track time that follows any of them. Cretu, Stewart and Berends, in Risk Management for Design and Construction, set out the risk-based estimate. The base cost is estimated without risks but with its own uncertainty. Each risk is entered with a probability of occurring and a range of cost if it does, and the two are combined by Monte Carlo simulation into a probability distribution of total cost. The budget is then chosen at a stated confidence, and the difference from the base cost is the contingency. Bissonette's Project Risk Management covers the register itself: naming risks precisely, assigning an owner, and retiring risks as the work goes on.
8.2.8.1 Method
Equation 8.2-1. Expected value and contingency
EMV = Σ pi × (ai + mi + bi)/3 (triangular mean of each risk's cost)
Contingency = Pconf − base cost, where Pconf is the simulated cost not exceeded at the chosen confidence
The expected value alone is a poor budget. A risk with a 25% chance of a $100,000 cost adds $25,000 to the average, yet the project will see either nothing or the full $100,000. The simulated distribution shows how often the budget is enough, and a P80 budget (enough four times in five) is one common choice; the owner sets the level. The calculator uses a fixed random seed so results repeat, and it checks its simulated mean against the analytical mean.
8.2.8.2 Worked example
A $2.4 million track and subgrade job (base range −5% to +15%) carries five ground risks, from a 30% chance of extra undercut in soft subgrade to a 25% chance of an unmarked utility. The risks' expected value is $130,250, and the simulated mean of $2,611,507 agrees with the analytical mean of $2,610,250. The P50 cost is $2,598,694 and the P80 cost is $2,743,855, so the contingency to P80 is $343,855, about 14% of base. That is well above the expected value of the risks because the budget has to cover the bad years, not the average one.
The register is only as good as its correlations. If one high water table drives both the dewatering risk and the soft-subgrade risk, enter them as one combined risk or the simulation will understate the spread. Every site-review finding from Chapter 3.4 and every boring result from Chapter 4.1 should either retire a risk or narrow its range.
Open the risk contingency calculator →
Monte Carlo combination of base-cost uncertainty and a register of ground risks into P50, P80 and P90 costs, with the expected value of each risk and the contingency to the chosen confidence.
8.2.8.3 Sources in the library
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads, clients and projects are not named.
- O. Cretu, R. Stewart and T. Berends, Risk Management for Design and Construction (Wiley, 2011): the risk-based estimate, base uncertainty, Monte Carlo analysis and confidence levelsFind source ↗
- M.M. Bissonette, Project Risk Management: A Practical Implementation Approach (PMI, 2016): building and maintaining a risk register, expected monetary value and risk responseFind source ↗
- Construction Inspection Manual, 8th edition: documenting changed conditions in the fieldFind source ↗