GHRMCalculators · Chapter 8.2, Section 8.2.8

Risk-Based Contingency

Companion to Chapter 8.2 · Change Orders, Section 8.2.8 Risk-Based Contingency for Ground-Related Change Orders. English units throughout.

Sketch of the inputs

risk-contingencytotal cost ($)cumulative probabilityconfidence levelbudgetbaseBase cost range; each risk: probability, low / most likely / high cost; N iterations

Monte Carlo total cost from the base range plus each risk; the contingency is the budget at the chosen confidence level minus the base cost. Not to scale.

Use and limitations

This calculator implements the method described in the manual section linked above. It is for planning, checking and teaching; design values must come from site-specific data, the governing railroad and agency standards, and the judgment of the responsible engineer.

Sources in the library

GHRM · Railway Ground Hazard Risk Management · Daniel P. Colwell