Table 8.2-1. Common causes of change on railroad geotechnical work| Cause | Example | Assumption it departs from (Chapter 3.1) |
|---|
| Train standby beyond the assumption | Heavy traffic gives far more standby than the hours per day assumed | Standby hours per day |
| Added borings or depths | A design check finds a reach with embankment work and no borings; three borings are added | Boring plan |
| Differing site conditions | Cemented slag or shallow rock causes refusal and offsets; soft clay continues below the planned depth | Expected profile |
| Access | Wet ground needs mats; borings plot outside the right-of-way and need a permit or right-of-entry | Access and right-of-entry |
| Impacted material | Odor or screening readings require drummed cuttings and extra tests | Cuttings spread on site |
| Additional analyses or deliverables | Client adds an alternative or asks for a report instead of a memorandum | Deliverable |
| Schedule | Flagging or client approvals delay mobilization; a second mobilization is needed | Schedule and number of setups |