8.2.1 Common Triggers

Handling changes in scope, conditions or schedule after the work has started, without stopping the work or losing the money.
Author: Daniel P. Colwell
8.2.1 Common Triggers
Table 8.2-1. Common causes of change on railroad geotechnical work
CauseExampleAssumption it departs from (Chapter 3.1)
Train standby beyond the assumptionHeavy traffic gives far more standby than the hours per day assumedStandby hours per day
Added borings or depthsA design check finds a reach with embankment work and no borings; three borings are addedBoring plan
Differing site conditionsCemented slag or shallow rock causes refusal and offsets; soft clay continues below the planned depthExpected profile
AccessWet ground needs mats; borings plot outside the right-of-way and need a permit or right-of-entryAccess and right-of-entry
Impacted materialOdor or screening readings require drummed cuttings and extra testsCuttings spread on site
Additional analyses or deliverablesClient adds an alternative or asks for a report instead of a memorandumDeliverable
ScheduleFlagging or client approvals delay mobilization; a second mobilization is neededSchedule and number of setups
Standby assumed for budgeting, hours per drilling day3.5 hrTypical drilling day, hours10 hrStandby can be a third of the day on a busy line
Figure 8.2-1. On one line the average train standby was about 3.5 hours per drilling day, more than a third of a 10-hour day. Stating that figure as an assumption makes any excess a clear change rather than a dispute.