8.2.4 Approval Workflow

Handling changes in scope, conditions or schedule after the work has started, without stopping the work or losing the money.
Author: Daniel P. Colwell
8.2.4 Approval Workflow
Table 8.2-4. Approval workflow
StepWhoOutput
Identify and notifyField engineer or project managerPhone call and email to the client project manager
Prepare the changeProject managerDescription, reason, cost breakdown, schedule effect
Internal reviewGeotechnical lead and the consultant's project manager for the clientAgreed scope and number
Client approvalClient project managerSigned change order or written approval
Subconsultant changeProject managerRevised subconsultant authorization
TrackProject managerBudget tracking updated by task

Where the work must continue to avoid a second mobilization (refusal on the last boring, an extra day of standby), get approval by email on the day and follow with the formal change. Do not stop a rig waiting for paperwork unless the client asks.