| Step | Who | Output |
|---|---|---|
| Identify and notify | Field engineer or project manager | Phone call and email to the client project manager |
| Prepare the change | Project manager | Description, reason, cost breakdown, schedule effect |
| Internal review | Geotechnical lead and the consultant's project manager for the client | Agreed scope and number |
| Client approval | Client project manager | Signed change order or written approval |
| Subconsultant change | Project manager | Revised subconsultant authorization |
| Track | Project manager | Budget tracking updated by task |
Where the work must continue to avoid a second mobilization (refusal on the last boring, an extra day of standby), get approval by email on the day and follow with the formal change. Do not stop a rig waiting for paperwork unless the client asks.