8.2.2 Notification and Documentation

Handling changes in scope, conditions or schedule after the work has started, without stopping the work or losing the money.
Author: Daniel P. Colwell
8.2.2 Notification and Documentation

Tell the client project manager as soon as a change is recognized, by phone and then in a short email, before the extra cost is spent where possible. Field staff call the project manager before leaving site each day; that call is where most changes are first heard.

Table 8.2-2. What to record for every change
RecordSource
What changed, where and whenField log, daily log, boring logs, photos
Why (the cause and the assumption it departs from)Proposal assumptions; RFP
Who was told, when, and what they saidEmail, phone record
Quantities (hours, footage, days, mats, tests)Daily logs; driller's field tickets; standby summary
Effect on schedule and deliverablesProject manager
Keep a standby log. Record train standby by day and by boring (start, end, reason) on the daily log and have the driller's ticket match it. A standby summary from past invoices on the same line is also the best basis for the next estimate.