Price a change with the same rates and structure as the original estimate (Chapter 3.7), so it can be checked line by line. Subconsultant changes are priced from their quote (standby rate, footage rate, mobilization). Show the net change and the new total.
| Line | Amount |
|---|---|
| Original agreement amount | $ |
| Net increase or decrease of this change | $ |
| Total of previous changes | $ |
| Total of all changes to date | $ |
| New agreement amount | $ |
| Change in time (working days) |
The same summary appears on standard construction change order forms; it lets the client see the cumulative effect of every change.
When a revision reduces the cost (for example, laboratory quantities reset to match the RFP, or a location dropped), issue it the same way. A credit documented promptly builds the trust that makes the next increase easier to approve.