3.10.2 Screening for Mining

Abandoned mines, buried structures, utilities and old works: hazards that people put in the ground, and how to find them before they find the project.
Author: Daniel P. Colwell
3.10.2 Screening for Mining
  • State mine-map repositories and abandoned mine land inventories; historic topographic maps showing mine symbols, tipples, spoil and openings.
  • Coal seam depth and thickness from geologic maps and nearby well and boring logs.
  • LiDAR for subsidence pits, strip-mine benches, spoil piles and filled openings.
  • Railroad records: spurs to tipples, mine-support agreements, repeated maintenance at the same locations.
  • Field reconnaissance: pits, cracks, ponding in new depressions, acid mine drainage (orange staining) at the toe of embankments.

Where screening shows mined seams within roughly 20 times their thickness of the surface, drill to below the seam with continuous coring, logging voids, rubble and water. Mine voids often hold water under pressure; plan for it. Treatment options include grouting the voids (low-mobility grout to form barriers, then flowable fill), excavating and backfilling shallow workings, and bridging. Grouting is covered in Chapter 7.2.