3.10.7 Worked Example

Abandoned mines, buried structures, utilities and old works: hazards that people put in the ground, and how to find them before they find the project.
Author: Daniel P. Colwell
3.10.7 Worked Example
The example uses a generic site and is not taken from any client project. It follows the five-part format.
Example 3.10-1: Screening Abandoned Room-and-Pillar Workings Under an Embankment

A state mine map shows room-and-pillar workings in a 6-ft coal seam below a section of track. A boring near the track found the seam at 45 ft depth, with shale roof rock. A shallow pit appeared in a field 300 ft away last year.

Given

VariableValueDescription
m6 ftMined height (seam thickness)
C45 ftDepth of cover over the workings
k1.3Bulking factor assumed for caved shale
Screening ratiosC/m < 10: sinkhole subsidence possible; > 20: unlikelySection 3.10.1

Required

  • Maximum height of void migration
  • Cover ratio and screening result
  • Whether further investigation is needed

Equations

  1. Eq. 3.10-1: Hmax = m/(k − 1) — maximum chimney height
  2. Eq. 2: C/m — cover ratio

Steps

Step 1 · Void migration height
Hmax = 6 / (1.3 − 1) = 6 / 0.3
Hmax ≈ 20 ft
Spot check: Each foot of void needs about 3.3 ft of caved rock to fill it at k = 1.3: 6 × 3.3 = 20 ft.
↓
Step 2 · Remaining cover
45 − 20
25 ft of cover above the highest likely chimney
Spot check: Positive, so a chimney alone would not reach the surface at k = 1.3.
↓
Step 3 · Cover ratio
C/m = 45 / 6
7.5 < 10: sinkhole subsidence possible
Spot check: Ratio and observed pit nearby both point to susceptibility.
↓
Solution
The simple bulking estimate gives a chimney height of about 20 ft, but the cover ratio of 7.5 is below the screening limit of 10 and a pit has formed nearby. The section is susceptible to sinkhole subsidence and needs investigation.

Solution

The simple bulking estimate gives a chimney height of about 20 ft, but the cover ratio of 7.5 is below the screening limit of 10 and a pit has formed nearby. The section is susceptible to sinkhole subsidence and needs investigation.

The two screens give different signals, and that is common. The bulking estimate assumes the caved rock fills the void evenly; in practice water can carry debris away into the mine, and weak shale may bulk less than assumed, so chimneys can go higher. The nearby pit is direct evidence that they do here. The cover ratio, which is calibrated on such observations, governs.

Next steps: obtain the mine map at the best available scale and overlay it in the KMZ, drill and core to below the seam at several points under the track, and if open voids or rubble are found, plan a grout program to fill the workings under and beside the track. Until then the section should carry a risk rating of at least 4 and be added to the inspection list after heavy rain.