2.13.6 Worked Example

Soils formed in place by weathering, and soils shaped by dry climates: why the usual sedimentary-soil rules do not fit them.
Author: Daniel P. Colwell
2.13.6 Worked Example
The example uses a generic site and is not taken from any client project. It follows the five-part format.
Example 2.13-1: Excavation Classes in a Piedmont Cut

A new rail cut 400 ft long and 26 ft deep at its centerline is planned in Piedmont saprolite. The control boring shows residual soil and saprolite to 22 ft, PWR (N ≥ 100 bpf) from 22 to 30 ft and auger refusal at 30 ft. For a first quantity split, the cut is idealized as a 60-ft-wide prism (the side slopes are handled separately).

Given

VariableValueDescription
L × B400 ft × 60 ft = 24,000 sq ftPlan area of the idealized cut
Soil and saprolite0 to 22 ftCommon excavation
PWR22 to 30 ftN ≥ 100 bpf; ripping or light blasting
Cut depth26 ftBottom of cut is in PWR
Conversion27 cf = 1 cyCubic feet to cubic yards

Required

  • Volume of common excavation
  • Volume of PWR excavation
  • Whether rock blasting is expected within the cut

Equations

  1. Eq. 1: V = A × t / 27 — volume of a layer in cubic yards

Steps

Step 1 · Common excavation
V = 24,000 × 22 / 27
V ≈ 19,600 cy
Spot check: 24,000 × 22 = 528,000 cf; ÷ 27 ≈ 19,600 cy.
↓
Step 2 · PWR excavation
Thickness in cut = 26 − 22 = 4 ft; V = 24,000 × 4 / 27
V ≈ 3,600 cy
Spot check: 4/22 of the common volume: 19,600 × 0.18 ≈ 3,560 cy. Consistent.
↓
Step 3 · Rock
Cut bottom at 26 ft; refusal at 30 ft
No rock excavation at the control boring
Spot check: Only 4 ft of margin above refusal, so rock is possible where the profile rises.
↓
Solution
At the control boring the idealized cut contains about 19,600 cy of common excavation and 3,600 cy of PWR, with refusal 4 ft below grade.

Solution

At the control boring the idealized cut contains about 19,600 cy of common excavation and 3,600 cy of PWR, with refusal 4 ft below grade.

A single boring cannot carry these quantities: in Piedmont terrain the PWR and refusal surfaces can rise or fall 10 ft or more within a few tens of feet. Additional borings along the cut, or a seismic refraction line along the centerline, are needed before quantities are bid, and the bid items should include a unit price for rock in case refusal rises into the cut.

The report should state the PWR definition used (N ≥ 100 bpf) so that the contractor can relate the quantities to equipment: PWR in this definition can often be ripped with a large dozer, while material below refusal generally needs blasting.