2.13.5 Investigation and Parameter Selection

Soils formed in place by weathering, and soils shaped by dry climates: why the usual sedimentary-soil rules do not fit them.
Author: Daniel P. Colwell
2.13.5 Investigation and Parameter Selection
  • Record moisture state and relict structure in the logs; describe saprolite with both its soil classification and its parent rock (e.g., "micaceous silty sand (saprolite of mica schist)").
  • Plot SPT N against depth for each boring; in residual profiles the trend is more informative than individual values.
  • Define PWR consistently on the logs (for example, N ≥ 100 bpf or less than 6 in. of advance in 50 blows) and state the definition in the report, since bid quantities depend on it.
  • Use test pits to see structure and caliche continuity; use rock coring below auger refusal to separate boulders from bedrock (core at least 10 ft into rock at critical locations).
  • Test arid soils at natural moisture and after wetting (collapse and swell tests); report both.
  • Use local correlations and experience where available; the standard sedimentary correlations for friction angle and modulus from N are often conservative for saprolite and unconservative for cemented arid soils that will be wetted.