A test pit is the cheapest way to see the ground, and every pit is an excavation under OSHA 29 CFR 1926 Subpart P; one 5 ft or deeper needs a protective system unless it is in stable rock. Reese and Eidson's Handbook of OSHA Construction Safety and Health reprints the standard. Its Appendix A classifies soil as stable rock or Type A, B or C from strength and condition, and Appendix B gives the maximum slope for each type. A trench box, shoring or sloping is required at 5 ft or more unless the cut is in stable rock. Anyone entering a pit to log or sample it is covered, and that is the usual reason an exploration pit is sloped or boxed. Next to track the railroad's own clearances apply as well.
| Type | Definition (summary) | Maximum slope (H:V), excavations under 20 ft |
|---|---|---|
| Stable rock | Natural solid mineral matter that stays intact when exposed | Vertical |
| A | Cohesive soil with qu of 1.5 tsf or more; not fissured, not subject to vibration, not previously disturbed, no layers dipping into the cut, no seepage | 3/4:1 (1/2:1 if open 24 hours or less and 12 ft or less deep) |
| B | Cohesive soil with qu over 0.5 and under 1.5 tsf; angular gravel, silt, silt loam, sandy loam; Type A soil that is fissured or subject to vibration; previously disturbed soil | 1:1 |
| C | Cohesive soil with qu of 0.5 tsf or less; gravel, sand, loamy sand; submerged soil or soil with water freely seeping; layers dipping into the cut at 4H:1V or steeper | 1½:1 |
| Requirement | Limit | Source |
|---|---|---|
| Protective system | Required at 5 ft or more except in stable rock | Subpart P |
| Engineer-designed protection | Deeper than 20 ft | Subpart P |
| Means of egress | Ladder, stair or ramp within 25 ft of lateral travel at 4 ft or more | Subpart P |
| Spoil and equipment | At least 2 ft back from the edge | Subpart P |
| Inspection | Daily and after rain or other changes, by a competent person | Subpart P |
| Track clearance for excavations | No closer than 12 ft to centerline; flagman within 25 ft; clear the 25 ft zone when trains pass | Railroad temporary shoring guidelines |
| Utility excavations and bores | 20 ft minimum from centerline | AREMA Chapter 1, Part 5 |
An 8 ft deep, 4 ft by 10 ft pit in stiff clay (pocket penetrometer 1.8 tsf), 30 ft from track. By strength alone the clay is Type A, but train vibration drops it to Type B, so the sides must be laid back at 1:1 and the top opening grows to 20.0 x 26.0 ft for 70.3 cu yd of excavation. Away from track the same clay would be Type A at 0.5H:1V (open less than a day and no deeper than 12 ft). A 6 ft pit 15 ft from centerline would need a flagman, and its sloped opening would reach within 12 ft of centerline. That pit has to be shored or boxed, not sloped.
Open the test pit safety calculator →
OSHA soil type from strength and conditions, the need for a protective system, maximum allowable slope, top opening and volume, egress, and railroad clearance warnings.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads, clients and projects are not named.