An investigation adds the engineering: interpretation of the data, the analyses the project needs, and specific recommendations. For railroad work typical analyses are track subgrade support and settlement, slope stability of fills and cuts (with and without the trigger condition), culvert bearing and settlement, foundations for bridges, signals and light towers, pavement subgrade parameters for yards, and the ground hazard risk rating with alternatives (Chapter 3.8).
| Project | Outputs |
|---|---|
| Siding or new main | Subgrade parameters; undercut and stabilization; cut and fill slope recommendations; culvert recommendations |
| Steepened or widened fill | Global stability (factor of safety 1.5 long-term); toe key, buttress or reinforcement alternatives; quantities by reach |
| Yard or intermodal pavement | Subgrade CBR, k and resilient modulus; undercut; geosynthetics or reclamation; light-tower shaft design |
| Bridge or culvert | Foundation type, capacity and settlement; lateral pile design; scour considerations |
| Ground hazard site | Current risk rating; alternatives with risk reduction ratings and costs (Sections 3.8.21 to 3.8.39) |