5.5.6 Worked Example

Designing for the most probable conditions, measuring what actually happens, and having the response ready before the measurements arrive.
Author: Daniel P. Colwell
5.5.6 Worked Example
The example uses a generic site and is not taken from any client project. Trigger values are illustrative; each site needs its own. It follows the five-part format.
Example 5.5-1: Evaluating Inclinometer Readings Against a TARP

A slow-moving slide below a fill slope is being operated under monitoring until stabilization is built. An inclinometer through the slip surface is read every 30 days. The site TARP sets amber at a rate above 0.25 in./month or a month-over-month acceleration ratio above 1.25, and red at a rate above 1.0 in./month or any track geometry defect attributable to the slide.

Given

VariableValueDescription
Reading 00.42 in.Cumulative displacement at slip surface, day 0
Reading 10.71 in.Day 30
Reading 21.15 in.Day 60
Amber> 0.25 in./month, or Ra > 1.25Alert trigger
Red> 1.0 in./month, or track defectAlarm trigger

Required

  • Displacement rates in the two intervals
  • Acceleration ratio
  • TARP level and action

Equations

  1. Eq. 1: v = Δd / Δt — displacement rate
  2. Eq. 5.5-1: Ra = v2/v1 — acceleration ratio

Steps

Step 1 · Rate, interval 1
v1 = (0.71 − 0.42) / 1 month
0.29 in./month
Spot check: Already just above the 0.25 in./month amber rate.
↓
Step 2 · Rate, interval 2
v2 = (1.15 − 0.71) / 1 month
0.44 in./month
Spot check: Annualized: 0.44 × 12 ≈ 5.3 in./yr.
↓
Step 3 · Acceleration ratio
Ra = 0.44 / 0.29
1.52 > 1.25
Spot check: The rate has increased by about half in one month.
↓
Step 4 · Compare with red
0.44 < 1.0 in./month; no track defect reported
Not red
↓
Solution
The slide is moving at 0.44 in./month and accelerating (Ra = 1.52). The site is at Amber on both rate and acceleration, but below Red.

Solution

The slide is moving at 0.44 in./month and accelerating (Ra = 1.52). The site is at Amber on both rate and acceleration, but below Red.

Amber actions apply: increase reading frequency (weekly, or install an automated in-place sensor), have the engineer review groundwater and rainfall records for a cause, inspect the track geometry over the slide, and confirm that the contingency measures in the TARP (for example, a toe berm and a speed restriction) are ready to deploy.

At 5 in./year the slide would be classed as very slow on the standard landslide velocity scale, which can make it seem harmless. The acceleration is what matters: if the rate increased by the same ratio again it would be near 0.7 in./month next month and could reach the red level within two or three months. In the live risk rating the site's frequency score should be raised until the trend reverses.