- Assign responsibilities in writing: who reads the instruments, who reviews, who can impose a speed restriction, and how fast each must act.
- Automate data delivery where the response time is short; a manual reading every month cannot support a response needed within hours.
- Set a baseline before construction or before the wet season so that later readings have a reference.
- Plan the contingency measures in enough detail that they can be built quickly: materials stockpiled, contractor available, access confirmed.
- Record decisions. The value of the method depends on showing that each trigger was acted on.
Close-out of a monitored project should include the readings, trigger exceedances and actions taken, which feed back into the risk rating for the site (Chapter 8.4).