The observational method was formalized in geotechnical practice in the late 1960s (Peck, 1969) as a way to save cost on projects where designing for the worst credible conditions would be very expensive, provided the work can be changed during construction. It is not "build it and see": the essential part is that the measurements and the responses are decided before work starts.
Railroad ground hazard management uses the same idea continuously. A landslide that is too costly to stabilize at once can be operated under monitoring, with speed restrictions or track inspection triggered by measured movement or rainfall, until the stabilization is funded and built.