A trigger-action response plan lists, for each monitored quantity, the levels at which action is taken and what that action is. Three levels are customary:
| Level | Meaning | Typical actions |
|---|---|---|
| Green (normal) | Behavior within the range predicted for most probable conditions | Continue routine monitoring |
| Amber (alert) | Behavior outside the predicted range, or accelerating | Increase monitoring frequency; engineer review within days; inspect track; prepare contingency measures |
| Red (alarm) | Behavior approaching the unfavorable case, or a track defect | Notify operations immediately; speed restriction or track out of service; implement contingency measures |
For slow-moving slopes, both the rate and the change in rate matter. A steady rate of an inch a year may be tolerable for decades; any rate that is accelerating month over month is a warning. A simple acceleration ratio is useful:
Trigger values are site-specific. They should be derived from the predicted behavior (for amber) and from the behavior at which the track or structure is no longer safe (for red), and they should be reviewed after the first few months of readings.