5.5.1 Elements of the Method

Designing for the most probable conditions, measuring what actually happens, and having the response ready before the measurements arrive.
Author: Daniel P. Colwell
5.5.1 Elements of the Method
Table 5.5-1. Elements of the observational method
StepContent
1. ExplorationEnough to establish the general nature, pattern and properties of the deposits, though not necessarily in detail
2. AssessmentThe most probable conditions and the most unfavorable conceivable deviations from them
3. DesignBased on the most probable conditions
4. Selection of quantities to observeWhat to measure, and the values expected under the most probable conditions
5. CalculationThe same quantities under the most unfavorable conditions
6. Pre-planned actionsA course of action or design change for every foreseeable significant deviation
7. ObservationMeasure the selected quantities and evaluate actual conditions
8. ModificationChange the design or operation to suit actual conditions

The method is suitable only where the behavior can be observed in time to act, and where a response is available that can be carried out quickly enough. It is not suitable for brittle failures that give no warning, such as some rock falls and cover-collapse sinkholes.