Chapter 5.5 — The Observational Method and Trigger-Action Response Plans

Designing for the most probable conditions, measuring what actually happens, and having the response ready before the measurements arrive.
Author: Daniel P. Colwell

Ground conditions are never fully known. The observational method accepts that and builds the uncertainty into the design: design for the most probable conditions, decide in advance what would show the conditions are worse, monitor for exactly that, and have a pre-planned response ready to put into effect. On railroads the same logic governs the monitoring of slow-moving slopes and settling embankments under traffic, where the trigger-action response plan (TARP) is the working document. This chapter describes the method, how to set trigger levels and how it connects to the GHRM live risk rating.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
5.5.0 Purpose and Overview

The observational method was formalized in geotechnical practice in the late 1960s (Peck, 1969) as a way to save cost on projects where designing for the worst credible conditions would be very expensive, provided the work can be changed during construction. It is not "build it and see": the essential part is that the measurements and the responses are decided before work starts.

Railroad ground hazard management uses the same idea continuously. A landslide that is too costly to stabilize at once can be operated under monitoring, with speed restrictions or track inspection triggered by measured movement or rainfall, until the stabilization is funded and built.

5.5.1 Elements of the Method
Table 5.5-1. Elements of the observational method
StepContent
1. ExplorationEnough to establish the general nature, pattern and properties of the deposits, though not necessarily in detail
2. AssessmentThe most probable conditions and the most unfavorable conceivable deviations from them
3. DesignBased on the most probable conditions
4. Selection of quantities to observeWhat to measure, and the values expected under the most probable conditions
5. CalculationThe same quantities under the most unfavorable conditions
6. Pre-planned actionsA course of action or design change for every foreseeable significant deviation
7. ObservationMeasure the selected quantities and evaluate actual conditions
8. ModificationChange the design or operation to suit actual conditions

The method is suitable only where the behavior can be observed in time to act, and where a response is available that can be carried out quickly enough. It is not suitable for brittle failures that give no warning, such as some rock falls and cover-collapse sinkholes.

5.5.2 Choosing What to Measure
Table 5.5-2. Common observed quantities on railroad ground hazard sites
HazardQuantityInstrument
Embankment on soft groundSettlement, pore pressure, lateral toe movementSettlement plates, piezometers, inclinometers
Slow-moving landslideDisplacement rate at the slip surface, groundwater levelInclinometers, ShapeArrays, piezometers, survey prisms
Cut slope in rockCrack opening, rockfall countsCrackmeters, extensometers, inspection
Retaining structureWall movement, anchor loadsSurvey, tiltmeters, load cells
Any hazard under trafficTrack geometry (surface, cross-level, alignment)Track geometry car, manual measurements
Rainfall-triggered hazardsRainfall intensity and antecedent rainfall, river stageRain gauges, stream gauges, forecasts

Instrumentation types and installation are covered in Chapter 5.3. The measurement should be directly related to the mechanism: for a landslide, displacement at the slip surface and the groundwater level that drives it.

5.5.3 Trigger Levels and the TARP

A trigger-action response plan lists, for each monitored quantity, the levels at which action is taken and what that action is. Three levels are customary:

Table 5.5-3. Typical TARP structure
LevelMeaningTypical actions
Green (normal)Behavior within the range predicted for most probable conditionsContinue routine monitoring
Amber (alert)Behavior outside the predicted range, or acceleratingIncrease monitoring frequency; engineer review within days; inspect track; prepare contingency measures
Red (alarm)Behavior approaching the unfavorable case, or a track defectNotify operations immediately; speed restriction or track out of service; implement contingency measures

For slow-moving slopes, both the rate and the change in rate matter. A steady rate of an inch a year may be tolerable for decades; any rate that is accelerating month over month is a warning. A simple acceleration ratio is useful:

Ra = vi / vi−1(Eq. 5.5-1)
vi = displacement rate in the latest reading interval; vi−1 = rate in the previous equal interval. Ra persistently above 1 signals acceleration.

Trigger values are site-specific. They should be derived from the predicted behavior (for amber) and from the behavior at which the track or structure is no longer safe (for red), and they should be reviewed after the first few months of readings.

5.5.4 Connection to the GHRM Live Risk Rating

The live risk rating described with the risk assessment (Chapter 3.8) is an observational method applied to a whole network. Each site has a baseline frequency and severity rating; measured quantities (rainfall, river stage, instrument readings) raise the frequency rating when they cross site thresholds. The TARP for a site is the action half of the same system: when the live rating jumps, the TARP says what happens next. Writing the two together keeps the thresholds consistent.

5.5.5 Making It Work
  • Assign responsibilities in writing: who reads the instruments, who reviews, who can impose a speed restriction, and how fast each must act.
  • Automate data delivery where the response time is short; a manual reading every month cannot support a response needed within hours.
  • Set a baseline before construction or before the wet season so that later readings have a reference.
  • Plan the contingency measures in enough detail that they can be built quickly: materials stockpiled, contractor available, access confirmed.
  • Record decisions. The value of the method depends on showing that each trigger was acted on.

Close-out of a monitored project should include the readings, trigger exceedances and actions taken, which feed back into the risk rating for the site (Chapter 8.4).

5.5.6 Worked Example
The example uses a generic site and is not taken from any client project. Trigger values are illustrative; each site needs its own. It follows the five-part format.
Example 5.5-1: Evaluating Inclinometer Readings Against a TARP

A slow-moving slide below a fill slope is being operated under monitoring until stabilization is built. An inclinometer through the slip surface is read every 30 days. The site TARP sets amber at a rate above 0.25 in./month or a month-over-month acceleration ratio above 1.25, and red at a rate above 1.0 in./month or any track geometry defect attributable to the slide.

Given

VariableValueDescription
Reading 00.42 in.Cumulative displacement at slip surface, day 0
Reading 10.71 in.Day 30
Reading 21.15 in.Day 60
Amber> 0.25 in./month, or Ra > 1.25Alert trigger
Red> 1.0 in./month, or track defectAlarm trigger

Required

  • Displacement rates in the two intervals
  • Acceleration ratio
  • TARP level and action

Equations

  1. Eq. 1: v = Δd / Δt — displacement rate
  2. Eq. 5.5-1: Ra = v2/v1 — acceleration ratio

Steps

Step 1 · Rate, interval 1
v1 = (0.71 − 0.42) / 1 month
0.29 in./month
Spot check: Already just above the 0.25 in./month amber rate.
↓
Step 2 · Rate, interval 2
v2 = (1.15 − 0.71) / 1 month
0.44 in./month
Spot check: Annualized: 0.44 × 12 ≈ 5.3 in./yr.
↓
Step 3 · Acceleration ratio
Ra = 0.44 / 0.29
1.52 > 1.25
Spot check: The rate has increased by about half in one month.
↓
Step 4 · Compare with red
0.44 < 1.0 in./month; no track defect reported
Not red
↓
Solution
The slide is moving at 0.44 in./month and accelerating (Ra = 1.52). The site is at Amber on both rate and acceleration, but below Red.

Solution

The slide is moving at 0.44 in./month and accelerating (Ra = 1.52). The site is at Amber on both rate and acceleration, but below Red.

Amber actions apply: increase reading frequency (weekly, or install an automated in-place sensor), have the engineer review groundwater and rainfall records for a cause, inspect the track geometry over the slide, and confirm that the contingency measures in the TARP (for example, a toe berm and a speed restriction) are ready to deploy.

At 5 in./year the slide would be classed as very slow on the standard landslide velocity scale, which can make it seem harmless. The acceleration is what matters: if the rate increased by the same ratio again it would be near 0.7 in./month next month and could reach the red level within two or three months. In the live risk rating the site's frequency score should be raised until the trend reverses.

5.5.7 Cross-References