This chapter covers how geotechnical and ground hazard cost estimates are built: the task structure, labor hours, subconsultant quotes, travel and expenses, the checks to make before an estimate goes out, and the stabilization construction costs used to compare risk reduction alternatives. It follows the cost estimate workbook used in practice, task for task.
An estimate is a model of the work. Each line should be traceable to a part of the scope (Chapter 3.1) and each quantity to the boring plan (Chapter 3.3) or the access study (Chapter 3.6). When the scope changes, the estimate changes with it, and the history of changes is kept so the final number can be explained.
| Type | Basis | Use |
|---|---|---|
| Order of magnitude | Similar past jobs; footage and days | Screening a program or a budget request; ranking alternatives at the desk |
| Proposal estimate | Task-by-task hours, subconsultant quotes, travel plan | Fee for a specific scope; the normal case for field investigations |
| Construction estimate for alternatives | Quantities and unit costs for stabilization | Comparing risk reduction alternatives (Chapter 3.8) |
Accuracy improves as the scope firms up. Say which type an estimate is, and carry a contingency that matches it rather than hiding uncertainty in the hours.
The workbook uses a fixed task list so that every estimate can be compared with every other. Only the tasks that apply are filled in.
| Task | Subtasks (typical) |
|---|---|
| A. Project management | Setup, coordination, meetings, invoicing, quality control |
| B. Ground hazard risk management | Desktop study, field assessment, risk rating, alternatives |
| C. Engineer reconnaissance | Mobilization, on site, demobilization, reconnaissance expenses |
| D. Subsurface field exploration | Utility clearance, mobilization, on-site exploration, demobilization, field expenses and drilling subconsultant |
| E. Laboratory testing | Laboratory management; soil, soil-cement and rock tests (in-house or subconsultant) |
| F. Geotechnical engineering | Boring logs, analysis, reporting |
| G. Pavement design | Only where requested |
| H to M | Survey; hydrology and hydraulics; structures; environmental permitting; bid package; construction quality assurance |
The consultant's field cost is mostly the field engineer's time with the rig: every drilling day, plus mobilization, utility clearance and demobilization. The drilling subconsultant's quote is entered as a lump sum and checked against the RFP quantities line by line (footage, coring, tubes, standby hours, mobilizations).
| Item | Basis |
|---|---|
| Utility clearance | Hours for one-call coordination and railroad signal and utility locates |
| Mobilization and demobilization | Travel time each way; one per separate setup |
| On-site exploration | Drilling days x hours per day (10-hour days are common with union crews) |
| Drilling subconsultant | Quote: mobilization, footage, coring, tubes, DCP, backfill, standby, per diem |
| Field expenses | Travel, lodging, vehicle, supplies |
Price the laboratory program from the test list in the RFP (Chapter 3.3). Where the drilling subconsultant's laboratory runs the tests, carry its lump sum and set the consultant's laboratory lines to zero so the client is not billed twice. Compare the two options when both are possible; on one recent job a reset of the subconsultant's lab quantities to match the RFP (fewer moisture contents and two triaxial tests dropped) took about 8 percent off the laboratory cost.
| Item | Basis |
|---|---|
| Airfare | 120 percent of the average round-trip fare for the route, to allow for booking late |
| Lodging | Hotel nearest the site at the client-allowed nightly rate, for every drilling night |
| Rental car and fuel | Per day on site |
| Per diem | Client or federal rates |
| Who travels | The field engineer for every drilling day; the senior engineer for a one-day reconnaissance where needed |
Write the travel plan into the estimate in a sentence ("the design engineer flies in, rents a car, stays at the hotel nearest the gate and is with the rig every drilling day; the senior engineer makes a one-night reconnaissance trip") so the client can see what it is paying for.
Engineering hours follow the deliverable. In the example of Figure 3.7-1, 92 hours covered typed logs (14), analysis (42) and reporting (36) for drilled-shaft design, pavement subgrade parameters, undercut and settlement. A memorandum addendum with stability analyses and quantities for a few reaches takes fewer; a full ground hazard assessment with alternatives takes more. Round all hours to the nearest half hour and bill them at the client's current rate schedule.
| Check | Why |
|---|---|
| The quote matches the RFP quantities | Quotes often carry different footage, tube or test counts |
| Laboratory carried once | Avoids double billing |
| The total in the email equals the workbook total | Small differences cause questions later; correct them in writing |
| Within any budget limit | Price separate locations as separate lines so the client can authorize one |
| Assumptions listed | Standby, access, flagging, utilities, cuttings, lab quantities (Chapter 3.1) |
| Revision history | Each revision dated, with the change and the net effect |
For ground hazard work the estimate also prices the stabilization alternatives, so that the risk reduction of each (Section 3.8.37) can be weighed against its cost. Build these from quantities by reach (shot rock, over-excavation, geotextile, geogrid, piles, lagging, drainage) and unit costs, and report a range rather than a single figure until the design is done.
| Alternative | Main quantities |
|---|---|
| Shot-rock toe key and buttress | Over-excavation, shot rock, geotextile, by reach |
| Geogrid-reinforced slope | Geogrid by layer, select fill, facing |
| Soldier pile and lagging wall | Piles (length and size), lagging, tiebacks if needed, drainage |
| Drainage improvements | Culvert replacement or cleaning, ditches, subdrains, outlet protection |
| Undercut and replace | Excavation, haul, select fill, geosynthetics |
| Rockfall measures | Scaling, bolting, mesh, catchment ditch |
Carry contingency as named items rather than as padding: train standby, refusal offsets, coring, extra mobilizations, mats and clearing (Chapter 3.3, Table 3.3-10). For construction estimates of alternatives add a percentage contingency that matches the stage of design, and escalate to the expected construction year.
Once the work is authorized, track hours and costs by the same tasks used in the estimate. The budget tracking workbook compares spent to date with the estimate for each task and flags tasks running over, early enough to talk to the client before the money is gone. Where the work grows beyond the scope, the tracking record is the basis for a change order (Chapter 8.2).
| Topic | Refer to |
|---|---|
| Scope and assumptions | Chapter 3.1 |
| Drilling scope, RFP and contingencies | Chapter 3.3 |
| Access and clearing quantities | Chapter 3.6 |
| Risk reduction ratings | Sections 3.8.37 to 3.8.39 |
| Alternatives on the risk assessment report | Section 3.8.42 |
| Change orders | Chapter 8.2 |
The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this chapter, gathered here from across the manual in the November 2026 restructure: 4 tools (3 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).
| Cost Estimating | |||
|---|---|---|---|
| $ | Geotechnical Cost Database by StateUsed in Chapter 3.7, 3.7.14 State Cost Database | calculator | Open |
| $ | Track Section QuantitiesUsed in Chapter 3.7, 3.7.12 Track Section Quantities for Estimates | calculator | Open |
| $ | Earthwork Volumes, Shrinkage and HaulUsed in Chapter 3.7, 3.7.13 Earthwork Volumes, Shrinkage and Haul | calculator | Open |
| Project Management & Checklists | |||
| PM | Budget TrackingUsed in Chapter 3.9, 3.9.1 Background — Why Planning is a Billable Deliverable | guide only | Guide |
Most of the cost of new or rebuilt track below the ties lies in four items: ballast, subballast, undercut of unsuitable subgrade, and its replacement. All four follow from the typical section and the boring results. Railroad sidetrack standards fix the section (12 in. of ballast below the tie on main track, ballast sloped 2:1, subballast to a set width and depth) and the undercut rules. A common rule removes plastic soils (AASHTO A-2-6, A-2-7, A-4 to A-7) in cuts to at least 2 ft below subgrade from ditch line to ditch line. It also removes organic muck (A-8) under fills within the toes of slope, to a width of three times the fill height where the fill exceeds 10 ft, and removes rock 18 in. below subgrade and refills it.
Equation 3.7-1. Net ballast area per foot of track
W1 = tie length + 2 shoulders (+ track centers for multiple tracks); W2 = W1 + 2 × slope × height; hb = ballast below tie; td, bt, Lt = tie depth, width and length; s = tie spacing.
| Item | Quantity |
|---|---|
| Net ballast area | 19.35 sq ft per ft |
| Ballast | 5,109 tons (3,784 cu yd) |
| Subballast | 9,660 tons (5,084 cu yd) |
| Undercut and replace, plastic subgrade in cut | 1,896 cu yd |
Unit weights (1.35 and 1.9 tons per cu yd) are entries, not standards; use the supplier's or railroad's conversion. Quantities are neat-line.
The undercut is often the item that the boring program changes most: if the borings show plastic soil over the whole of a cut rather than 800 ft of it, the undercut quantity and the haul double. Linking the estimate to the boring logs (Chapter 4.1) is the best protection against change orders (Chapter 8.2).
Open the track quantities calculator →
Ballast and subballast volume and tonnage from the typical section, with undercut and replacement of plastic subgrade and rock in cuts.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.
Sidings, yard expansions, realignments and slide repairs all start with an earthwork estimate: how much cut, how much fill, whether the cut will make the fill, and how many truckloads go off site or come in from a borrow pit. Volumes come from cross sections at regular stations; the shrinkage of soil compacted into fill and its swell when loaded for hauling turn the neat volumes into the quantities that are bought, moved and paid for.
Equation 3.7-2. Earthwork volume between stations
A1, A2 = end areas (ft²); Am = area of the section half-way between them, whose coordinates are the averages of the end sections; L = distance between stations (ft); divide by 27 for cubic yards.
The average-end-area method overestimates where the areas differ greatly; the prismoidal formula corrects this when the middle section is known. The cumulative difference between cut and bank-adjusted fill along the line (the mass diagram) shows where material can be moved within the job and where it must be wasted or borrowed.
A 400-ft siding extension on a Class I railroad located in Kansas runs from fill, through a cut, back into fill. Cross sections every 100 ft give the cut and fill areas below. The cut is a lean clay with 10% shrinkage and 25% swell; trucks carry 14 loose cubic yards.
| Variable | Value | Description |
|---|---|---|
| Sta 0+00 | Cut 0, fill 400 ft² | |
| Sta 1+00 | Cut 300, fill 250 ft² | |
| Sta 2+00 | Cut 900, fill 0 ft² | |
| Sta 3+00 | Cut 600, fill 50 ft² | |
| Sta 4+00 | Cut 0, fill 500 ft² | |
| Shrinkage, swell | 10%; 25% | Lean clay |
| Truck | 14 cy loose |
The cut makes all of the fill with about 3,600 cy to spare, so the job needs a waste site, not a borrow pit.
Only the surplus needs to leave the site: about 3,580 × 1.25 / 14 = 320 truckloads. Before planning to reuse the clay as fill, confirm it can be compacted at its natural water content (Section 5.3.2.5); a wet clay that must be dried or replaced changes the balance and the cost.
Open the earthwork volume calculator →
Average-end-area and prismoidal volumes from a table of stations, shrinkage and swell, waste or borrow, truckloads, an optional unit cost, and the mass diagram.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.
Where cut or fill is measured on a grid rather than on cross sections, as for a borrow pit, a yard pad or a slide excavation, the volume is:
V = [ A / (4 × 27) ] ( Σh1 + 2Σh2 + 3Σh3 + 4Σh4 ) (yd³)
A = area of one grid square (ft²); h1, h2, h3, h4 = cut or fill depths (ft) at grid corners shared by one, two, three and four squares.
The area of an irregular end area or site boundary can be computed from the coordinates of its corners: A = ½ | Σ (xi yi+1 − xi+1 yi) |.
For railroad work: Use the grid method for borrow sources, yard and pad grading, and for the volume of a slide mass or remedial excavation from survey grids or lidar differences, then apply shrinkage and swell as in this section.
Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 212, Earthwork.
A shrinkage percentage taken from a table is only an estimate. When the density and moisture of the borrow soil and the compaction requirement are known, the borrow quantity can be computed directly. Water can be added to the soil or dried out of it, but the mass of solids does not change between the borrow pit and the fill, so it links the two:
Ws = γd,fill × Vfill γd,borrow = γwet,borrow / (1 + wborrow) Vbank = Ws / γd,borrow
Water to add = Ws (wfill − wborrow) / 8.34 (gallons)
where γd,fill is the specified dry unit weight (for example 95% of the Proctor maximum), wfill is the placement moisture content, and the borrow values are measured in the pit. The equivalent shrinkage factor is 1 − γd,borrow/γd,fill. A negative result for the water means the borrow is too wet and must be dried by disking and aeration, which takes dry weather and time. Always work in dry unit weights. Using the ratio of wet unit weights mixes the water change into the volume change and gives the wrong borrow quantity (Example 3.7-3).
For railroad work: Use this method when a borrow source is sampled for a siding, embankment widening or slide repair. Measure the borrow pit’s in-place density and moisture at several depths, because both usually vary down the face. Carry the water quantity into the estimate as its own item, with the water source, hauling and any permit. Large quantities are common on embankment work, and in dry country the water can cost as much as the haul.
Source: Rajapakse, R. (2016). Geotechnical Engineering Calculations and Rules of Thumb, 2nd ed. Oxford: Butterworth-Heinemann, Ch. 38 (earthwork; borrow pit problems, Practice Problem 38.6). Summarized and paraphrased; the shrinkage-factor link and recommendations for railroad work are added by the authors of this manual.
A new passing siding for a Class I railroad located in Missouri needs 12,000 cy of compacted embankment fill. The specification calls for 95% of a standard Proctor maximum dry unit weight of 118 pcf, placed at the optimum moisture of 12.5%. A nearby borrow pit has an in-place wet unit weight of 115 pcf at 8% moisture. The borrow soil swells 25% when loaded, and trucks carry 14 loose cubic yards. The engineer must find the borrow volume, the water to add, and the number of truckloads.
| Variable | Value | Description |
|---|---|---|
| Vfill | 12,000 cy = 324,000 ft³ | Compacted fill required |
| γd,fill | 0.95 × 118 = 112.1 pcf | Specified dry unit weight |
| wfill | 12.5% | Placement moisture (optimum) |
| γwet,borrow, wborrow | 115 pcf, 8% | Borrow pit in place |
| Swell; truck | 25%; 14 cy loose | Haul |
(a) Ws = 36.3 million lb. (b) Excavate about 12,630 cy (bank), an equivalent shrinkage of 5%. (c) Add about 196,000 gallons of water. (d) About 1,130 truckloads.
The low shrinkage reflects a borrow soil that is already fairly dense in place. A table value of 10 to 15% would have overstated the borrow by about 700 to 1,500 cy. The water is a real cost item: at 16 gallons per cubic yard, a water truck of 4,000 gallons covers only about 250 cy of fill. Add the water in the pit or on the spread lift and mix it in before compaction, not as a surface spray. Re-measure the pit moisture after rain, because a few points wetter turns a water-adding job into a drying job.
Sections 3.7.2 to 3.7.8 explain how an estimate is built; this section supplies the unit costs. The database holds 168 geotechnical cost items in 2026 dollars, from drilling footage and laboratory tests through soldier pile walls, rock bolts and wick drains, with a low, typical and high value for each. Each state gets its own price for every item. Where a state DOT or a state contract has published a price, that price is used. Elsewhere the national value is scaled by a location factor for the state.
Use the database the way an experienced estimator uses a bid history: to size a budget before quotes exist, to check a subcontractor's quote line by line, and to show a client how much the same scope costs in a different state. It does not replace quotes. Railroad work in particular tends to price above highway averages, because flagging, work windows and access from the track add time that a highway contractor does not carry.
Equation 3.7-3. Unit cost of an item in a state
Equation 3.7-4. Estimate total
Cnat = national typical unit cost; Fs = state location factor (1.00 = national average); Q = quantity; m = mobilization as a fraction of construction; c = contingency; e = annual escalation; n = years from 2026 to the midpoint of the work.
Three groups are not adjusted by F: laboratory tests, engineering labor and travel. Their rates follow the firm and the laboratory, not the site, and samples are shipped. Railroad flagging is not adjusted either, because each railroad sets its own rate. The low and high values are the national range times F. Where a published state price falls outside that range, the range is widened to include it.
The location factors are area cost factors developed for building construction. They capture the labor and equipment markets that drive most geotechnical costs. They are not meant to be applied to unit prices, which is why a published state price always takes precedence. Hawaii and Alaska factors (above 2.0) reflect remote building work; check them against local quotes before using them.
Every item carries a basis code that tells the user how much to trust it. DOT means a statewide average of recent bid prices. FEE means a published fee schedule or a state drilling contract. LAB means a 2026 regional laboratory fee schedule, with a range of 0.75 to 1.35 times the listed rate. HIST means older bid data escalated to 2026 with the FHWA National Highway Construction Cost Index, which doubled between 2003 and 2021 and has risen more than half again since. EST means a planning value compiled for this manual. Replace EST values with local quotes first.
| Phase | Group | Items | Examples | Basis (count) |
|---|---|---|---|---|
| Design | Drilling and sampling | 19 | Mobilization, HSA and mud-rotary footage, coring, tubes, rig day rate | EST 4, FEE 15 |
| Design | In situ testing and geophysics | 19 | CPTu, DMT, dissipation, vane, MASW, ERT, GPR, piezometers | EST 7, FEE 5, LAB 7 |
| Design | Laboratory testing | 34 | Moisture, Atterberg, gradation, consolidation, triaxial, rock UCS, corrosivity, aggregate durability | LAB 34 |
| Design | Engineering labor (billing rates) | 8 | Principal through administrative | EST 8 |
| Design | Site access, safety and field expenses | 10 | Flagging, right-of-entry, insurance, locates, travel | EST 10 |
| Construction | Earthwork, undercut and fill | 10 | Excavation, rock, undercut, borrow, embankment, haul, waste | DOT 7, EST 3 |
| Construction | Track substructure and aggregates | 4 | Ballast, subballast, track undercutting, HMA underlayment | DOT 1, EST 3 |
| Construction | Geosynthetics | 6 | Separation and stabilization geotextile, geogrid, geocell | DOT 3, EST 3 |
| Construction | Drainage and erosion protection | 11 | Riprap, filter blanket, gabions, underdrains, horizontal drains | DOT 6, EST 4, HIST 1 |
| Construction | Deep foundations | 12 | Drilled shafts, H-piles, micropiles, load tests | DOT 7, EST 5 |
| Construction | Retaining structures | 12 | Soldier pile walls, tiebacks, sheet piles, CIP, MSE, soil nails | DOT 2, EST 6, HIST 4 |
| Construction | Slope and rock stabilization | 9 | Scaling, rock bolts, drapery, barriers, buttresses, reinforced slopes | EST 7, HIST 2 |
| Construction | Ground improvement | 10 | Wick drains, surcharge, lime/cement, mass mixing, stone columns, grouting | DOT 3, EST 7 |
| Construction | General conditions | 4 | Mobilization, flagging, survey, instrument readings | EST 4 |
| State | F | Prices | State | F | Prices | State | F | Prices |
|---|---|---|---|---|---|---|---|---|
| Alabama | 0.86 | Kentucky | 0.87 | North Dakota | 1.17 | |||
| Alaska | 2.28 | 2 | Louisiana | 0.93 | Ohio | 0.98 | ||
| Arizona | 0.89 | Maine | 1.11 | 2 | Oklahoma | 0.89 | 1 | |
| Arkansas | 0.86 | 13 | Maryland | 1.01 | Oregon | 1.13 | ||
| California | 1.24 | Massachusetts | 1.18 | Pennsylvania | 1.06 | |||
| Colorado | 1.06 | Michigan | 1.03 | Rhode Island | 1.16 | |||
| Connecticut | 1.10 | Minnesota | 1.11 | 2 | South Carolina | 0.95 | ||
| Delaware | 1.09 | Mississippi | 0.83 | South Dakota | 0.98 | |||
| District of Columbia | 1.04 | Missouri | 0.96 | Tennessee | 0.87 | 12 | ||
| Florida | 0.96 | Montana | 1.04 | Texas | 0.82 | |||
| Georgia | 0.88 | Nebraska | 0.98 | Utah | 0.99 | |||
| Hawaii | 2.15 | Nevada | 1.16 | Vermont | 1.03 | |||
| Idaho | 1.04 | New Hampshire | 1.06 | Virginia | 0.88 | 5 | ||
| Illinois | 1.01 | New Jersey | 1.18 | Washington | 1.10 | 4 | ||
| Indiana | 0.92 | New Mexico | 0.90 | West Virginia | 0.97 | 13 | ||
| Iowa | 0.98 | New York | 1.07 | Wisconsin | 1.07 | |||
| Kansas | 0.92 | North Carolina | 0.85 | Wyoming | 0.98 |
The database starts with the published prices below. They come from state DOT average-price reports, a statewide geotechnical drilling bid, a state drilling services contract, a state maximum-cost drilling rule and a published CPT fee schedule. Add to them from the average bid price reports most DOTs publish each year. Look at the quantity behind each average: a price on a few hundred feet of horizontal drains or 18 cy of gabions says little about a large job. Statewide averages also mix mass-grading jobs with small repairs. A low unclassified-excavation average (under $5/cy in one state) reflects large balanced cuts, not a railroad slide repair.
| State | Item | Unit | Price | Year | Pay item / note |
|---|---|---|---|---|---|
| Alaska | Geotextile, separation | SY | $2.35 | 2025 | Geotextile Type A separation, 501-10,000 SY |
| Alaska | Riprap, by weight | TON | $221.42 | 2025 | Riprap Class III, 1-100 ton |
| Arkansas | Unclassified excavation (common) | CY | $17.12 | 2025 | Item 210 unclassified excavation, 502,489 CY |
| Arkansas | Compacted embankment | CY | $20.06 | 2025 | Item 210 compacted embankment |
| Arkansas | Select granular backfill | CY | $50.52 | 2025 | Item 210 select granular backfill |
| Arkansas | Subballast / aggregate base course | TON | $41.04 | 2025 | Item 303 aggregate base course Class 7 |
| Arkansas | Riprap, dumped | CY | $129.02 | 2025 | Item 816 dumped riprap |
| Arkansas | Riprap, by weight | TON | $57.37 | 2025 | Item 816 foundation protection riprap |
| Arkansas | Filter blanket (bedding stone) | SY | $9.86 | 2025 | Item 816 filter blanket |
| Arkansas | Underdrain, 4-6 in. perforated pipe with stone | LF | $19.76 | 2025 | Item 611 4 in. pipe underdrains |
| Arkansas | Steel H-pile HP12x53, furnished and driven | LF | $135.00 | 2025 | Item 805 steel piling HP12x53 (388 LF) |
| Arkansas | Steel H-pile HP14x73, furnished and driven | LF | $147.07 | 2025 | Item 805 steel piling HP14x73 |
| Arkansas | Dynamic pile load test (PDA) | EA | $10,000 | 2025 | Item 805 dynamic pile load test |
| Arkansas | Lime or cement stabilized subgrade, processing | SY | $7.21 | 2025 | Item 308 processing cement-stabilized base |
| Arkansas | Cement for stabilization | TON | $233.91 | 2025 | Item 307 cement in full-depth reclaimed base |
| Maine | Drill rig mobilization, truck rig (within 100 mi) | EA | $550.00 | 2025 | Mobilization (land) |
| Maine | Drill rig and crew, day rate (standby, clearing, extra work) | DAY | $2,550 | 2025 | Drill rig (land), per day |
| Minnesota | Hollow-stem auger boring with SPT at 5-ft intervals, 0-50 ft | LF | $35.00 | 2022 | Hollow-stem auger, per foot beyond 25 ft |
| Minnesota | Mobilization beyond 50 mi, per mile one way | MI | $9.00 | 2022 | Mobilization per mile over 50 mi |
| Oklahoma | Unclassified excavation (common) | CY | $10.80 | 2025 | 202(A) unclassified excavation, all regions |
| Tennessee | Unclassified excavation (common) | CY | $14.81 | 2024 | 203-01 road and drainage excavation (unclassified) |
| Tennessee | Undercut and removal of unsuitable material | CY | $10.55 | 2024 | 203-05 undercutting |
| Tennessee | Borrow excavation, common | CY | $19.47 | 2024 | 203-03 borrow excavation (unclassified) |
| Tennessee | Select borrow / select fill | CY | $27.91 | 2024 | 203-03.01 borrow excavation (select material) |
| Tennessee | Subballast / aggregate base course | TON | $37.35 | 2024 | 303-01 mineral aggregate Type A base, Grading D |
| Tennessee | Drilled shaft, 48-72 in., in soil | LF | $1,053 | 2024 | 625-02.01 drilled shaft, soil (per VF) |
| Tennessee | Drilled shaft, rock socket | LF | $2,432 | 2024 | 625-02.13 drilled shaft, rock (per VF) |
| Tennessee | Drilled shaft permanent casing | LF | $1,520 | 2024 | 625-02.25 permanent casing (per VF) |
| Tennessee | Drilled shaft integrity (CSL or thermal) / camera inspection | EA | $1,786 | 2024 | 625-01.11 camera inspection, wet shaft |
| Tennessee | Horizontal drain, drilled | LF | $13.50 | 2024 | 610-12.02 horizontal drains (338 LF only) |
| Tennessee | Steel sheet piling, temporary | SF | $32.44 | 2024 | 606-24.12 temporary sheet piles |
| Tennessee | Cast-in-place concrete retaining wall (wall face) | SF | $173.81 | 2024 | 604-07 retaining wall items, quantity-weighted (12 items, 107,995 SF) |
| Virginia | CPT rig mobilization | EA | $1,200 | 2026 | Truck rig mobilization |
| Virginia | Piezocone sounding (CPTu) | LF | $17.50 | 2026 | CPTu geotechnical sounding, per ft |
| Virginia | Pore pressure dissipation test | EA | $400.00 | 2026 | Pore pressure dissipation test |
| Virginia | Flat dilatometer (DMT) sounding | LF | $30.00 | 2026 | DMT at 20-cm intervals, per ft |
| Virginia | Seismic cone shear-wave test (per depth) | EA | $50.00 | 2026 | Seismic test at 1.0-m intervals |
| Washington | Hollow-stem auger boring with SPT at 5-ft intervals, 0-50 ft | LF | $75.00 | 2022 | Hollow-stem auger with SPT every 5 ft, 0-50 ft |
| Washington | Mud rotary boring with SPT, 0-50 ft | LF | $75.00 | 2022 | Mud rotary 0-50 ft |
| Washington | Rock coring, NQ or HQ, with core boxes | LF | $150.00 | 2022 | Rock coring and sampling 0-50 ft |
| Washington | Casing advance (over water, cobbles, fill) | LF | $150.00 | 2022 | Casing advance 0-50 ft |
| West Virginia | Unclassified excavation (common) | CY | $4.67 | 2025 | 207001-001 unclassified excavation; mass grading jobs pull the average down |
| West Virginia | Borrow excavation, common | CY | $45.27 | 2025 | 211001-000 unclassified borrow excavation |
| West Virginia | Rock excavation | CY | $71.04 | 2025 | 211002-000 rock borrow excavation (CY) |
| West Virginia | Select borrow / select fill | CY | $125.24 | 2025 | 211003-000 select borrow (851 CY) |
| West Virginia | Prefabricated vertical (wick) drains | LF | $1.25 | 2025 | 206001-001 prefabricated wick drains |
| West Virginia | Subballast / aggregate base course | TON | $53.12 | 2025 | 307005-001 aggregate base course, stone or gravel (ton) |
| West Virginia | Riprap, dumped | CY | $151.96 | 2025 | 218001-000 riprap |
| West Virginia | Geotextile, subsurface drainage / filter | SY | $1.40 | 2025 | 207032-000 fabric for subsurface drainage |
| West Virginia | Geotextile, subgrade stabilization | SY | $2.00 | 2025 | 207033-000 fabric for subgrade stabilization |
| West Virginia | Geotextile, separation | SY | $2.39 | 2025 | 207034-000 fabric for separation |
| West Virginia | Gabion | CY | $712.91 | 2025 | 218003-000 gabion (18 CY) |
| West Virginia | Underdrain, 4-6 in. perforated pipe with stone | LF | $21.82 | 2025 | 606025-002 4 in. underdrain pipe |
| West Virginia | Aggregate-filled fabric underdrain / french drain | LF | $49.32 | 2025 | 606020-001 aggregate-filled fabric underdrain |
A slip at the toe of a track embankment is to be repaired with a cantilever soldier pile and lagging wall, 120 ft long with 14 ft exposed, after the soft toe soil is undercut and replaced with select granular backfill on a separation geotextile. An underdrain runs behind the wall and riprap protects the ditch. The same repair is needed at two sites on a Class I railroad, one located in Tennessee and one located in Pennsylvania. The client wants a budget for each before it releases design.
| Variable | Value | Description |
|---|---|---|
| Aw | 1,680 sf | Soldier pile and lagging wall face |
| Vu | 600 cy | Undercut unsuitable toe soil |
| Vb | 600 cy | Select granular backfill |
| Ag | 900 sy | Separation geotextile |
| Vr | 150 cy | Riprap at the ditch |
| Ld | 240 lf | Underdrain behind the wall |
| Nf | 20 days | Railroad flagging |
| FTN, FPA | 0.87; 1.06 | State location factors (Table 3.7-10) |
| m, c | 7%; 20% | Mobilization (construction only); contingency |
| e, n | 3% per year; 1 yr | Escalation to the midpoint of construction |
| Item | Qty | Unit | Unit cost basis | Unit cost | Cost |
|---|---|---|---|---|---|
| Tennessee | |||||
| Soldier pile and lagging wall face | 1,680 | SF | $110 × 0.87 | $96 | $160,776 |
| Undercut unsuitable toe soil | 600 | CY | published TN price (2024) | $11 | $6,330 |
| Select granular backfill | 600 | CY | $50 × 0.87 | $44 | $26,100 |
| Separation geotextile | 900 | SY | $2.50 × 0.87 | $2.17 | $1,957 |
| Riprap at the ditch | 150 | CY | $130 × 0.87 | $113 | $16,965 |
| Underdrain behind the wall | 240 | LF | $22 × 0.87 | $19 | $4,594 |
| Railroad flagging | 20 | DAY | not location-adjusted | $1,200 | $24,000 |
| Pennsylvania | |||||
| Soldier pile and lagging wall face | 1,680 | SF | $110 × 1.06 | $117 | $195,888 |
| Undercut unsuitable toe soil | 600 | CY | $18 × 1.06 | $19 | $11,448 |
| Select granular backfill | 600 | CY | $50 × 1.06 | $53 | $31,800 |
| Separation geotextile | 900 | SY | $2.50 × 1.06 | $2.65 | $2,385 |
| Riprap at the ditch | 150 | CY | $130 × 1.06 | $138 | $20,670 |
| Underdrain behind the wall | 240 | LF | $22 × 1.06 | $23 | $5,597 |
| Railroad flagging | 20 | DAY | not location-adjusted | $1,200 | $24,000 |
Budget about $318,000 for the Tennessee site and $386,000 for the Pennsylvania site.
The wall is about 67% of the construction cost in both states, so the location factor on that one item drives most of the difference. Flagging is the same in both because the railroad sets the rate. Report the range ($190,000 to $534,000 in TN) with the typical figure until the wall is designed: pile size and embedment can move the wall unit cost by half in either direction. When the drilling and wall contractors quote, replace the database values with the quotes. The Estimate sheet of the Excel master is set up with these quantities and reproduces the PA total.
Open the state cost database and estimator → Download the Excel master
Pick a state, filter the items, enter quantities and get low, typical and high totals with mobilization, contingency and escalation, plus the same estimate in every state. The Excel master holds the same data with live formulas, so new state prices can be added as they are collected.
Treat the database as a living bid history. When a quote or bid comes in, add it to the State Prices sheet of the Excel master with its year and quantity, and it replaces national × F for that state. Escalate all values each year with the change in the NHCCI or the state's own cost index (Section 3.7.8). Review EST items against actual quotes at least once a year, and retire any published price older than about five years.
Unit costs are compiled from the public sources below; the summaries are in original wording. Individual railroads, clients, companies and projects are not named.