Chapter 3.7 — Cost Estimates

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell

This chapter covers how geotechnical and ground hazard cost estimates are built: the task structure, labor hours, subconsultant quotes, travel and expenses, the checks to make before an estimate goes out, and the stabilization construction costs used to compare risk reduction alternatives. It follows the cost estimate workbook used in practice, task for task.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
3.7.0 Purpose and Overview

An estimate is a model of the work. Each line should be traceable to a part of the scope (Chapter 3.1) and each quantity to the boring plan (Chapter 3.3) or the access study (Chapter 3.6). When the scope changes, the estimate changes with it, and the history of changes is kept so the final number can be explained.

Table 3.7-1. Estimate types and their uses
TypeBasisUse
Order of magnitudeSimilar past jobs; footage and daysScreening a program or a budget request; ranking alternatives at the desk
Proposal estimateTask-by-task hours, subconsultant quotes, travel planFee for a specific scope; the normal case for field investigations
Construction estimate for alternativesQuantities and unit costs for stabilizationComparing risk reduction alternatives (Chapter 3.8)

Accuracy improves as the scope firms up. Say which type an estimate is, and carry a contingency that matches it rather than hiding uncertainty in the hours.

3.7.1 Task Structure

The workbook uses a fixed task list so that every estimate can be compared with every other. Only the tasks that apply are filled in.

Table 3.7-2. Cost estimate tasks
TaskSubtasks (typical)
A. Project managementSetup, coordination, meetings, invoicing, quality control
B. Ground hazard risk managementDesktop study, field assessment, risk rating, alternatives
C. Engineer reconnaissanceMobilization, on site, demobilization, reconnaissance expenses
D. Subsurface field explorationUtility clearance, mobilization, on-site exploration, demobilization, field expenses and drilling subconsultant
E. Laboratory testingLaboratory management; soil, soil-cement and rock tests (in-house or subconsultant)
F. Geotechnical engineeringBoring logs, analysis, reporting
G. Pavement designOnly where requested
H to MSurvey; hydrology and hydraulics; structures; environmental permitting; bid package; construction quality assurance
A. Project management28 hrC. Engineer reconnaissance18 hrD. Field exploration91.5 hrE. Laboratory (management)6 hrF. Engineering (logs, analysis, report)92 hrLabor hours by task, 19-boring field investigation with report (235.5 hr total)
Figure 3.7-1. Labor hours by task for a recent 19-boring investigation. Field exploration and engineering each take about 40 percent of the hours; project management about 12 percent.
3.7.2 Field Exploration Costs

The consultant's field cost is mostly the field engineer's time with the rig: every drilling day, plus mobilization, utility clearance and demobilization. The drilling subconsultant's quote is entered as a lump sum and checked against the RFP quantities line by line (footage, coring, tubes, standby hours, mobilizations).

Table 3.7-3. Field exploration items
ItemBasis
Utility clearanceHours for one-call coordination and railroad signal and utility locates
Mobilization and demobilizationTravel time each way; one per separate setup
On-site explorationDrilling days x hours per day (10-hour days are common with union crews)
Drilling subconsultantQuote: mobilization, footage, coring, tubes, DCP, backfill, standby, per diem
Field expensesTravel, lodging, vehicle, supplies
Standby. Use the average standby from past work on the same line where it exists (3.5 hours per day on one line), and state it as an assumption. Many drillers include DCP testing in their day rate; ask, and do not price it twice.
3.7.3 Laboratory Testing Costs

Price the laboratory program from the test list in the RFP (Chapter 3.3). Where the drilling subconsultant's laboratory runs the tests, carry its lump sum and set the consultant's laboratory lines to zero so the client is not billed twice. Compare the two options when both are possible; on one recent job a reset of the subconsultant's lab quantities to match the RFP (fewer moisture contents and two triaxial tests dropped) took about 8 percent off the laboratory cost.

3.7.4 Travel and Expenses
Table 3.7-4. Travel basis used in the estimate workbook
ItemBasis
Airfare120 percent of the average round-trip fare for the route, to allow for booking late
LodgingHotel nearest the site at the client-allowed nightly rate, for every drilling night
Rental car and fuelPer day on site
Per diemClient or federal rates
Who travelsThe field engineer for every drilling day; the senior engineer for a one-day reconnaissance where needed

Write the travel plan into the estimate in a sentence ("the design engineer flies in, rents a car, stays at the hotel nearest the gate and is with the rig every drilling day; the senior engineer makes a one-night reconnaissance trip") so the client can see what it is paying for.

3.7.5 Engineering and Reporting Labor

Engineering hours follow the deliverable. In the example of Figure 3.7-1, 92 hours covered typed logs (14), analysis (42) and reporting (36) for drilled-shaft design, pavement subgrade parameters, undercut and settlement. A memorandum addendum with stability analyses and quantities for a few reaches takes fewer; a full ground hazard assessment with alternatives takes more. Round all hours to the nearest half hour and bill them at the client's current rate schedule.

3.7.6 Checking the Estimate
Table 3.7-5. Checks before an estimate goes out
CheckWhy
The quote matches the RFP quantitiesQuotes often carry different footage, tube or test counts
Laboratory carried onceAvoids double billing
The total in the email equals the workbook totalSmall differences cause questions later; correct them in writing
Within any budget limitPrice separate locations as separate lines so the client can authorize one
Assumptions listedStandby, access, flagging, utilities, cuttings, lab quantities (Chapter 3.1)
Revision historyEach revision dated, with the change and the net effect
35%43%18%TotalConsultant laborDrillingLaboratoryTravel and expensesLocation 1 estimate: about $93,000; with the second location: about $156,000 (over the $100,000 limit)
Figure 3.7-2. Make-up of a recent field investigation estimate. Pricing the two locations separately let the client authorize the one that fit its budget limit.
3.7.7 Stabilization Construction Costs

For ground hazard work the estimate also prices the stabilization alternatives, so that the risk reduction of each (Section 3.8.37) can be weighed against its cost. Build these from quantities by reach (shot rock, over-excavation, geotextile, geogrid, piles, lagging, drainage) and unit costs, and report a range rather than a single figure until the design is done.

Table 3.7-6. Typical stabilization cost items
AlternativeMain quantities
Shot-rock toe key and buttressOver-excavation, shot rock, geotextile, by reach
Geogrid-reinforced slopeGeogrid by layer, select fill, facing
Soldier pile and lagging wallPiles (length and size), lagging, tiebacks if needed, drainage
Drainage improvementsCulvert replacement or cleaning, ditches, subdrains, outlet protection
Undercut and replaceExcavation, haul, select fill, geosynthetics
Rockfall measuresScaling, bolting, mesh, catchment ditch
Compare like with like. When a client is weighing stabilization against buying land or easements, give quantities and a cost range for each alternative on the same basis, and say what each one leaves as residual risk.
3.7.8 Contingency and Escalation

Carry contingency as named items rather than as padding: train standby, refusal offsets, coring, extra mobilizations, mats and clearing (Chapter 3.3, Table 3.3-10). For construction estimates of alternatives add a percentage contingency that matches the stage of design, and escalate to the expected construction year.

Project cost control. An estimate is only useful if actual costs are tracked against it; budget tracking by task (Section 3.7.9) closes the loop.
Figure 3.7-3. Project cost control. An estimate is only useful if actual costs are tracked against it; budget tracking by task (Section 3.7.9) closes the loop.
3.7.9 Budget Tracking

Once the work is authorized, track hours and costs by the same tasks used in the estimate. The budget tracking workbook compares spent to date with the estimate for each task and flags tasks running over, early enough to talk to the client before the money is gone. Where the work grows beyond the scope, the tracking record is the basis for a change order (Chapter 8.2).

3.7.10 Cross-References
Table 3.7-7. Related chapters
TopicRefer to
Scope and assumptionsChapter 3.1
Drilling scope, RFP and contingenciesChapter 3.3
Access and clearing quantitiesChapter 3.6
Risk reduction ratingsSections 3.8.37 to 3.8.39
Alternatives on the risk assessment reportSection 3.8.42
Change ordersChapter 8.2
3.7.11 Apps and Tools4

The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this chapter, gathered here from across the manual in the November 2026 restructure: 4 tools (3 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).

Tools

Cost Estimating
$Geotechnical Cost Database by StateUsed in Chapter 3.7, 3.7.14 State Cost DatabasecalculatorOpen
$Track Section QuantitiesUsed in Chapter 3.7, 3.7.12 Track Section Quantities for EstimatescalculatorOpen
$Earthwork Volumes, Shrinkage and HaulUsed in Chapter 3.7, 3.7.13 Earthwork Volumes, Shrinkage and HaulcalculatorOpen
Project Management & Checklists
PMBudget TrackingUsed in Chapter 3.9, 3.9.1 Background — Why Planning is a Billable Deliverableguide onlyGuide
3.7.12 Track Section Quantities for Estimates

Most of the cost of new or rebuilt track below the ties lies in four items: ballast, subballast, undercut of unsuitable subgrade, and its replacement. All four follow from the typical section and the boring results. Railroad sidetrack standards fix the section (12 in. of ballast below the tie on main track, ballast sloped 2:1, subballast to a set width and depth) and the undercut rules. A common rule removes plastic soils (AASHTO A-2-6, A-2-7, A-4 to A-7) in cuts to at least 2 ft below subgrade from ditch line to ditch line. It also removes organic muck (A-8) under fills within the toes of slope, to a width of three times the fill height where the fill exceeds 10 ft, and removes rock 18 in. below subgrade and refills it.

3.7.12.1 Section geometry

Equation 3.7-1. Net ballast area per foot of track

Ab = (W1 + W2)/2 × (hb + td) − n Lt bt td / s

W1 = tie length + 2 shoulders (+ track centers for multiple tracks); W2 = W1 + 2 × slope × height; hb = ballast below tie; td, bt, Lt = tie depth, width and length; s = tie spacing.

3.7.12.2 Worked example: one mile of single track

Table 3.7-8. 8.5 ft ties at 19.5 in., 12 in. ballast, 12 in. shoulders, 2:1; 12 in. subballast 24 ft wide; 800 ft of plastic cut (calculator output)
ItemQuantity
Net ballast area19.35 sq ft per ft
Ballast5,109 tons (3,784 cu yd)
Subballast9,660 tons (5,084 cu yd)
Undercut and replace, plastic subgrade in cut1,896 cu yd

Unit weights (1.35 and 1.9 tons per cu yd) are entries, not standards; use the supplier's or railroad's conversion. Quantities are neat-line.

The undercut is often the item that the boring program changes most: if the borings show plastic soil over the whole of a cut rather than 800 ft of it, the undercut quantity and the haul double. Linking the estimate to the boring logs (Chapter 4.1) is the best protection against change orders (Chapter 8.2).

Open the track quantities calculator →
Ballast and subballast volume and tonnage from the typical section, with undercut and replacement of plastic subgrade and rock in cuts.

3.7.12.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • A Class I railroad's standard specifications for private sidetracks (2016), Carriers folder: roadbed and ballast sections, unsuitable material, embankments, subballast and ballast gradations.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1 (2019 edition), Part 2: ballast depth below tie and sub-ballast practice.Official page ↗
  • A Class I railroad's public projects manual (2020), Carriers folder.Find source ↗
3.7.13 Earthwork Volumes, Shrinkage and Haul

Sidings, yard expansions, realignments and slide repairs all start with an earthwork estimate: how much cut, how much fill, whether the cut will make the fill, and how many truckloads go off site or come in from a borrow pit. Volumes come from cross sections at regular stations; the shrinkage of soil compacted into fill and its swell when loaded for hauling turn the neat volumes into the quantities that are bought, moved and paid for.

3.7.13.1 Method

Equation 3.7-2. Earthwork volume between stations

Average end area: V = L(A1 + A2)/2;   Prismoidal: V = L(A1 + 4Am + A2)/6;   Bank volume for fill = Vfill/(1 − shrinkage);   Loose volume = Vbank(1 + swell)

A1, A2 = end areas (ft²); Am = area of the section half-way between them, whose coordinates are the averages of the end sections; L = distance between stations (ft); divide by 27 for cubic yards.

The average-end-area method overestimates where the areas differ greatly; the prismoidal formula corrects this when the middle section is known. The cumulative difference between cut and bank-adjusted fill along the line (the mass diagram) shows where material can be moved within the job and where it must be wasted or borrowed.

3.7.13.2 Worked example

Example 3.7-1: Grading a Siding Extension

A 400-ft siding extension on a Class I railroad located in Kansas runs from fill, through a cut, back into fill. Cross sections every 100 ft give the cut and fill areas below. The cut is a lean clay with 10% shrinkage and 25% swell; trucks carry 14 loose cubic yards.

gradecutfillfill0+001+002+003+004+00end areas every 100 ftGivenStations 0+00 to 4+00 at 100 ftCut and fill end areas (ft²)Shrinkage 10%, swell 25%Truck 14 cy looseRequiredCut and fill volumesWaste or borrowTruckloads
Profile of the siding extension: fill at both ends and a cut through the middle.

Given

VariableValueDescription
Sta 0+00Cut 0, fill 400 ft²
Sta 1+00Cut 300, fill 250 ft²
Sta 2+00Cut 900, fill 0 ft²
Sta 3+00Cut 600, fill 50 ft²
Sta 4+00Cut 0, fill 500 ft²
Shrinkage, swell10%; 25%Lean clay
Truck14 cy loose

Required

  • Cut and fill volumes
  • Waste or borrow
  • Truckloads to haul the cut

Equations

  1. Eq. 3.7-2: V = L(A1 + A2)/(2 × 27) — cy
  2. Eq. 3.7-2: Bank for fill = Vfill/(1 − 0.10)
  3. Eq. 3.7-2: Loose = Vcut × 1.25

Steps

Step 1 · Cut
100/54 × [(0 + 300) + (300 + 900) + (900 + 600) + (600 + 0)]
Vcut = 6,667 cy
↓
Step 2 · Fill
100/54 × [(400 + 250) + (250 + 0) + (0 + 50) + (50 + 500)]
Vfill = 2,778 cy
Spot check: Hicks’ two-section example (areas 1,504 and 2,240 ft², 100 ft apart) gives 6,933 cy by average end area and 6,904 cy prismoidal in the calculator, matching the handbook.
↓
Step 3 · Bank volume for the fill
2,778/0.90
3,086 cy
↓
Step 4 · Balance
6,667 − 3,086
Waste 3,580 cy (bank)
↓
Step 5 · Haul
6,667 × 1.25 = 8,333 loose cy; /14
596 truckloads if all cut is hauled
↓
Solution
Cut 6,667 cy, fill 2,778 cy; about 3,580 cy (bank) of surplus to waste.

Solution

The cut makes all of the fill with about 3,600 cy to spare, so the job needs a waste site, not a borrow pit.

Only the surplus needs to leave the site: about 3,580 × 1.25 / 14 = 320 truckloads. Before planning to reuse the clay as fill, confirm it can be compacted at its natural water content (Section 5.3.2.5); a wet clay that must be dried or replaced changes the balance and the cost.

Open the earthwork volume calculator →
Average-end-area and prismoidal volumes from a table of stations, shrinkage and swell, waste or borrow, truckloads, an optional unit cost, and the mass diagram.

3.7.13.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • T.G. Hicks (ed.), Handbook of Civil Engineering Calculations, McGraw-Hill (2000): Section 5, volume of earthwork (average-end-area and prismoidal methods).Find source ↗Library entry
Supplemental reference · Goswami (2015), Ch. 212

Borrow Pit (Grid) Volumes and Areas by Coordinates

Where cut or fill is measured on a grid rather than on cross sections, as for a borrow pit, a yard pad or a slide excavation, the volume is:

V = [ A / (4 × 27) ] ( Σh1 + 2Σh2 + 3Σh3 + 4Σh4 )   (yd³)

A = area of one grid square (ft²); h1, h2, h3, h4 = cut or fill depths (ft) at grid corners shared by one, two, three and four squares.

The area of an irregular end area or site boundary can be computed from the coordinates of its corners: A = ½ | Σ (xi yi+1 − xi+1 yi) |.

For railroad work: Use the grid method for borrow sources, yard and pad grading, and for the volume of a slide mass or remedial excavation from survey grids or lidar differences, then apply shrinkage and swell as in this section.

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 212, Earthwork.

Supplemental reference · Rajapakse (2016), Ch. 38

Borrow Volume From the Mass of Solids, and the Water to Add

A shrinkage percentage taken from a table is only an estimate. When the density and moisture of the borrow soil and the compaction requirement are known, the borrow quantity can be computed directly. Water can be added to the soil or dried out of it, but the mass of solids does not change between the borrow pit and the fill, so it links the two:

Ws = γd,fill × Vfill    γd,borrow = γwet,borrow / (1 + wborrow)    Vbank = Ws / γd,borrow
Water to add = Ws (wfill − wborrow) / 8.34  (gallons)

where γd,fill is the specified dry unit weight (for example 95% of the Proctor maximum), wfill is the placement moisture content, and the borrow values are measured in the pit. The equivalent shrinkage factor is 1 − γd,borrow/γd,fill. A negative result for the water means the borrow is too wet and must be dried by disking and aeration, which takes dry weather and time. Always work in dry unit weights. Using the ratio of wet unit weights mixes the water change into the volume change and gives the wrong borrow quantity (Example 3.7-3).

For railroad work: Use this method when a borrow source is sampled for a siding, embankment widening or slide repair. Measure the borrow pit’s in-place density and moisture at several depths, because both usually vary down the face. Carry the water quantity into the estimate as its own item, with the water source, hauling and any permit. Large quantities are common on embankment work, and in dry country the water can cost as much as the haul.

Source: Rajapakse, R. (2016). Geotechnical Engineering Calculations and Rules of Thumb, 2nd ed. Oxford: Butterworth-Heinemann, Ch. 38 (earthwork; borrow pit problems, Practice Problem 38.6). Summarized and paraphrased; the shrinkage-factor link and recommendations for railroad work are added by the authors of this manual.

Example 3.7-3: Borrow Quantity and Water for a Siding Embankment

A new passing siding for a Class I railroad located in Missouri needs 12,000 cy of compacted embankment fill. The specification calls for 95% of a standard Proctor maximum dry unit weight of 118 pcf, placed at the optimum moisture of 12.5%. A nearby borrow pit has an in-place wet unit weight of 115 pcf at 8% moisture. The borrow soil swells 25% when loaded, and trucks carry 14 loose cubic yards. The engineer must find the borrow volume, the water to add, and the number of truckloads.

Borrow pitγwet = 115 pcfw = 8%V bank = ? 14 cy loose; swell 25%loads = ? Siding fill12,000 cy95% of 118 pcf at 12.5% water to add = ? gal GivenFill: 12,000 cy compactedγd = 0.95 × 118 pcf; w = 12.5%Borrow: γwet = 115 pcf; w = 8%Swell 25%; truck 14 cy loose RequiredMass of solidsBorrow (bank) volumeWater to addTruckloads Black = given; red = required
Given and required for Example 3.7-3.

Given

VariableValueDescription
Vfill12,000 cy = 324,000 ft³Compacted fill required
γd,fill0.95 × 118 = 112.1 pcfSpecified dry unit weight
wfill12.5%Placement moisture (optimum)
γwet,borrow, wborrow115 pcf, 8%Borrow pit in place
Swell; truck25%; 14 cy looseHaul

Required

  • (a) Weight of solids in the fill
  • (b) Bank volume to excavate, and the equivalent shrinkage
  • (c) Water to add, in gallons
  • (d) Number of truckloads

Equations

  1. Eq. 1: Ws = γd,fill Vfill
  2. Eq. 2: γd,borrow = γwet/(1 + w); Vbank = Ws/γd,borrow
  3. Eq. 3: Water = Ws(wfill − wborrow)/8.34 — gallons
  4. Eq. 4: Loads = Vbank(1 + swell)/14

Steps

Step 1 · (a) Solids (Eq. 1)
112.1 × 324,000
Ws = 36.3 million lb
↓
Step 2 · (b) Bank volume (Eq. 2)
γd,borrow = 115/1.08 = 106.5 pcf; 36.32 × 106/106.5 = 341,100 ft³
Vbank = 12,630 cy; shrinkage = 1 − 106.5/112.1 = 5.0%
Spot check: 12,000/12,630 = 0.950. Using wet unit weights instead (126.1/115 × 12,000) gives 13,160 cy, about 530 cy too much.
↓
Step 3 · (c) Water (Eq. 3)
36.32 × 106 × (0.125 − 0.08) = 1.63 million lb; /8.34
About 196,000 gal (16 gal per cy of fill)
↓
Step 4 · (d) Truckloads (Eq. 4)
12,630 × 1.25 = 15,790 loose cy; /14
About 1,130 loads
↓
Solution
12,630 cy bank, 196,000 gal of water, about 1,130 loads.

Solution

(a) Ws = 36.3 million lb. (b) Excavate about 12,630 cy (bank), an equivalent shrinkage of 5%. (c) Add about 196,000 gallons of water. (d) About 1,130 truckloads.

The low shrinkage reflects a borrow soil that is already fairly dense in place. A table value of 10 to 15% would have overstated the borrow by about 700 to 1,500 cy. The water is a real cost item: at 16 gallons per cubic yard, a water truck of 4,000 gallons covers only about 250 cy of fill. Add the water in the pit or on the spread lift and mix it in before compaction, not as a surface spray. Re-measure the pit moisture after rain, because a few points wetter turns a water-adding job into a drying job.

3.7.14 State Cost Database for Geotechnical Design and Construction

Sections 3.7.2 to 3.7.8 explain how an estimate is built; this section supplies the unit costs. The database holds 168 geotechnical cost items in 2026 dollars, from drilling footage and laboratory tests through soldier pile walls, rock bolts and wick drains, with a low, typical and high value for each. Each state gets its own price for every item. Where a state DOT or a state contract has published a price, that price is used. Elsewhere the national value is scaled by a location factor for the state.

Use the database the way an experienced estimator uses a bid history: to size a budget before quotes exist, to check a subcontractor's quote line by line, and to show a client how much the same scope costs in a different state. It does not replace quotes. Railroad work in particular tends to price above highway averages, because flagging, work windows and access from the track add time that a highway contractor does not carry.

3.7.14.1 Method

Equation 3.7-3. Unit cost of an item in a state

Cs = CDOT,s where a published state price exists; otherwise Cs = Cnat × Fs

Equation 3.7-4. Estimate total

Total = [Σ(Q × Cs)design + Σ(Q × Cs)construction × (1 + m)] × (1 + c) × (1 + e)n

Cnat = national typical unit cost; Fs = state location factor (1.00 = national average); Q = quantity; m = mobilization as a fraction of construction; c = contingency; e = annual escalation; n = years from 2026 to the midpoint of the work.

Three groups are not adjusted by F: laboratory tests, engineering labor and travel. Their rates follow the firm and the laboratory, not the site, and samples are shipped. Railroad flagging is not adjusted either, because each railroad sets its own rate. The low and high values are the national range times F. Where a published state price falls outside that range, the range is widened to include it.

The location factors are area cost factors developed for building construction. They capture the labor and equipment markets that drive most geotechnical costs. They are not meant to be applied to unit prices, which is why a published state price always takes precedence. Hawaii and Alaska factors (above 2.0) reflect remote building work; check them against local quotes before using them.

3.7.14.2 What the database holds

Every item carries a basis code that tells the user how much to trust it. DOT means a statewide average of recent bid prices. FEE means a published fee schedule or a state drilling contract. LAB means a 2026 regional laboratory fee schedule, with a range of 0.75 to 1.35 times the listed rate. HIST means older bid data escalated to 2026 with the FHWA National Highway Construction Cost Index, which doubled between 2003 and 2021 and has risen more than half again since. EST means a planning value compiled for this manual. Replace EST values with local quotes first.

Table 3.7-9. Contents of the cost database (168 items)
PhaseGroupItemsExamplesBasis (count)
DesignDrilling and sampling19Mobilization, HSA and mud-rotary footage, coring, tubes, rig day rateEST 4, FEE 15
DesignIn situ testing and geophysics19CPTu, DMT, dissipation, vane, MASW, ERT, GPR, piezometersEST 7, FEE 5, LAB 7
DesignLaboratory testing34Moisture, Atterberg, gradation, consolidation, triaxial, rock UCS, corrosivity, aggregate durabilityLAB 34
DesignEngineering labor (billing rates)8Principal through administrativeEST 8
DesignSite access, safety and field expenses10Flagging, right-of-entry, insurance, locates, travelEST 10
ConstructionEarthwork, undercut and fill10Excavation, rock, undercut, borrow, embankment, haul, wasteDOT 7, EST 3
ConstructionTrack substructure and aggregates4Ballast, subballast, track undercutting, HMA underlaymentDOT 1, EST 3
ConstructionGeosynthetics6Separation and stabilization geotextile, geogrid, geocellDOT 3, EST 3
ConstructionDrainage and erosion protection11Riprap, filter blanket, gabions, underdrains, horizontal drainsDOT 6, EST 4, HIST 1
ConstructionDeep foundations12Drilled shafts, H-piles, micropiles, load testsDOT 7, EST 5
ConstructionRetaining structures12Soldier pile walls, tiebacks, sheet piles, CIP, MSE, soil nailsDOT 2, EST 6, HIST 4
ConstructionSlope and rock stabilization9Scaling, rock bolts, drapery, barriers, buttresses, reinforced slopesEST 7, HIST 2
ConstructionGround improvement10Wick drains, surcharge, lime/cement, mass mixing, stone columns, groutingDOT 3, EST 7
ConstructionGeneral conditions4Mobilization, flagging, survey, instrument readingsEST 4

3.7.14.3 State location factors

Table 3.7-10. State location factors F (1.00 = national average) and number of published state prices in the database
StateFPricesStateFPricesStateFPrices
Alabama0.86Kentucky0.87North Dakota1.17
Alaska2.282Louisiana0.93Ohio0.98
Arizona0.89Maine1.112Oklahoma0.891
Arkansas0.8613Maryland1.01Oregon1.13
California1.24Massachusetts1.18Pennsylvania1.06
Colorado1.06Michigan1.03Rhode Island1.16
Connecticut1.10Minnesota1.112South Carolina0.95
Delaware1.09Mississippi0.83South Dakota0.98
District of Columbia1.04Missouri0.96Tennessee0.8712
Florida0.96Montana1.04Texas0.82
Georgia0.88Nebraska0.98Utah0.99
Hawaii2.15Nevada1.16Vermont1.03
Idaho1.04New Hampshire1.06Virginia0.885
Illinois1.01New Jersey1.18Washington1.104
Indiana0.92New Mexico0.90West Virginia0.9713
Iowa0.98New York1.07Wisconsin1.07
Kansas0.92North Carolina0.85Wyoming0.98

3.7.14.4 Published state prices

The database starts with the published prices below. They come from state DOT average-price reports, a statewide geotechnical drilling bid, a state drilling services contract, a state maximum-cost drilling rule and a published CPT fee schedule. Add to them from the average bid price reports most DOTs publish each year. Look at the quantity behind each average: a price on a few hundred feet of horizontal drains or 18 cy of gabions says little about a large job. Statewide averages also mix mass-grading jobs with small repairs. A low unclassified-excavation average (under $5/cy in one state) reflects large balanced cuts, not a railroad slide repair.

Table 3.7-11. Published state prices loaded so far (54 values, 9 states)
StateItemUnitPriceYearPay item / note
AlaskaGeotextile, separationSY$2.352025Geotextile Type A separation, 501-10,000 SY
AlaskaRiprap, by weightTON$221.422025Riprap Class III, 1-100 ton
ArkansasUnclassified excavation (common)CY$17.122025Item 210 unclassified excavation, 502,489 CY
ArkansasCompacted embankmentCY$20.062025Item 210 compacted embankment
ArkansasSelect granular backfillCY$50.522025Item 210 select granular backfill
ArkansasSubballast / aggregate base courseTON$41.042025Item 303 aggregate base course Class 7
ArkansasRiprap, dumpedCY$129.022025Item 816 dumped riprap
ArkansasRiprap, by weightTON$57.372025Item 816 foundation protection riprap
ArkansasFilter blanket (bedding stone)SY$9.862025Item 816 filter blanket
ArkansasUnderdrain, 4-6 in. perforated pipe with stoneLF$19.762025Item 611 4 in. pipe underdrains
ArkansasSteel H-pile HP12x53, furnished and drivenLF$135.002025Item 805 steel piling HP12x53 (388 LF)
ArkansasSteel H-pile HP14x73, furnished and drivenLF$147.072025Item 805 steel piling HP14x73
ArkansasDynamic pile load test (PDA)EA$10,0002025Item 805 dynamic pile load test
ArkansasLime or cement stabilized subgrade, processingSY$7.212025Item 308 processing cement-stabilized base
ArkansasCement for stabilizationTON$233.912025Item 307 cement in full-depth reclaimed base
MaineDrill rig mobilization, truck rig (within 100 mi)EA$550.002025Mobilization (land)
MaineDrill rig and crew, day rate (standby, clearing, extra work)DAY$2,5502025Drill rig (land), per day
MinnesotaHollow-stem auger boring with SPT at 5-ft intervals, 0-50 ftLF$35.002022Hollow-stem auger, per foot beyond 25 ft
MinnesotaMobilization beyond 50 mi, per mile one wayMI$9.002022Mobilization per mile over 50 mi
OklahomaUnclassified excavation (common)CY$10.802025202(A) unclassified excavation, all regions
TennesseeUnclassified excavation (common)CY$14.812024203-01 road and drainage excavation (unclassified)
TennesseeUndercut and removal of unsuitable materialCY$10.552024203-05 undercutting
TennesseeBorrow excavation, commonCY$19.472024203-03 borrow excavation (unclassified)
TennesseeSelect borrow / select fillCY$27.912024203-03.01 borrow excavation (select material)
TennesseeSubballast / aggregate base courseTON$37.352024303-01 mineral aggregate Type A base, Grading D
TennesseeDrilled shaft, 48-72 in., in soilLF$1,0532024625-02.01 drilled shaft, soil (per VF)
TennesseeDrilled shaft, rock socketLF$2,4322024625-02.13 drilled shaft, rock (per VF)
TennesseeDrilled shaft permanent casingLF$1,5202024625-02.25 permanent casing (per VF)
TennesseeDrilled shaft integrity (CSL or thermal) / camera inspectionEA$1,7862024625-01.11 camera inspection, wet shaft
TennesseeHorizontal drain, drilledLF$13.502024610-12.02 horizontal drains (338 LF only)
TennesseeSteel sheet piling, temporarySF$32.442024606-24.12 temporary sheet piles
TennesseeCast-in-place concrete retaining wall (wall face)SF$173.812024604-07 retaining wall items, quantity-weighted (12 items, 107,995 SF)
VirginiaCPT rig mobilizationEA$1,2002026Truck rig mobilization
VirginiaPiezocone sounding (CPTu)LF$17.502026CPTu geotechnical sounding, per ft
VirginiaPore pressure dissipation testEA$400.002026Pore pressure dissipation test
VirginiaFlat dilatometer (DMT) soundingLF$30.002026DMT at 20-cm intervals, per ft
VirginiaSeismic cone shear-wave test (per depth)EA$50.002026Seismic test at 1.0-m intervals
WashingtonHollow-stem auger boring with SPT at 5-ft intervals, 0-50 ftLF$75.002022Hollow-stem auger with SPT every 5 ft, 0-50 ft
WashingtonMud rotary boring with SPT, 0-50 ftLF$75.002022Mud rotary 0-50 ft
WashingtonRock coring, NQ or HQ, with core boxesLF$150.002022Rock coring and sampling 0-50 ft
WashingtonCasing advance (over water, cobbles, fill)LF$150.002022Casing advance 0-50 ft
West VirginiaUnclassified excavation (common)CY$4.672025207001-001 unclassified excavation; mass grading jobs pull the average down
West VirginiaBorrow excavation, commonCY$45.272025211001-000 unclassified borrow excavation
West VirginiaRock excavationCY$71.042025211002-000 rock borrow excavation (CY)
West VirginiaSelect borrow / select fillCY$125.242025211003-000 select borrow (851 CY)
West VirginiaPrefabricated vertical (wick) drainsLF$1.252025206001-001 prefabricated wick drains
West VirginiaSubballast / aggregate base courseTON$53.122025307005-001 aggregate base course, stone or gravel (ton)
West VirginiaRiprap, dumpedCY$151.962025218001-000 riprap
West VirginiaGeotextile, subsurface drainage / filterSY$1.402025207032-000 fabric for subsurface drainage
West VirginiaGeotextile, subgrade stabilizationSY$2.002025207033-000 fabric for subgrade stabilization
West VirginiaGeotextile, separationSY$2.392025207034-000 fabric for separation
West VirginiaGabionCY$712.912025218003-000 gabion (18 CY)
West VirginiaUnderdrain, 4-6 in. perforated pipe with stoneLF$21.822025606025-002 4 in. underdrain pipe
West VirginiaAggregate-filled fabric underdrain / french drainLF$49.322025606020-001 aggregate-filled fabric underdrain

3.7.14.5 Worked example

Example 3.7-2: Pricing a Toe Wall Repair in Two States

A slip at the toe of a track embankment is to be repaired with a cantilever soldier pile and lagging wall, 120 ft long with 14 ft exposed, after the soft toe soil is undercut and replaced with select granular backfill on a separation geotextile. An underdrain runs behind the wall and riprap protects the ditch. The same repair is needed at two sites on a Class I railroad, one located in Tennessee and one located in Pennsylvania. The client wants a budget for each before it releases design.

track Aw = 1,680 sf (120 ft × 14 ft) Vu = Vb = 600 cy Ld = 240 lf, Ag = 900 sy Vr = 150 cy ? Cost in TN and PA Given Quantities Aw, Vu, Vb, Ag, Vr, Ld Flagging Nf = 20 days FTN = 0.87, FPA = 1.06 m = 7%, c = 20%, e = 3%/yr, n = 1 Required ? Construction cost in each state ? Low-high bounds ? Difference between the states black = given · red ? = required
Toe wall repair: wall, undercut and backfill, underdrain and ditch riprap.

Given

VariableValueDescription
Aw1,680 sfSoldier pile and lagging wall face
Vu600 cyUndercut unsuitable toe soil
Vb600 cySelect granular backfill
Ag900 sySeparation geotextile
Vr150 cyRiprap at the ditch
Ld240 lfUnderdrain behind the wall
Nf20 daysRailroad flagging
FTN, FPA0.87; 1.06State location factors (Table 3.7-10)
m, c7%; 20%Mobilization (construction only); contingency
e, n3% per year; 1 yrEscalation to the midpoint of construction

Required

  • Construction cost in each state, with mobilization, contingency and escalation
  • Low and high bounds
  • How much the location changes the budget

Equations

  1. Eq. 3.7-3: Cs = CDOT,s if published; else Cnat × Fs
  2. Eq. 3.7-4: Total = [Σ(Q Cs)design + Σ(Q Cs)constr(1 + m)](1 + c)(1 + e)n

Steps

Step 1 · Unit cost of each item in each state
Uses Eq. 3.7-3 and Table 3.7-11
Tennessee has a published undercut price ($10.55/cy, 2024), so it is used directly. Every other item is national typical × F; flagging is not adjusted.
See Table 3.7-12
Spot check: wall in PA: $110 × 1.06 = $116.60/sf; 1,680 × $116.60 = $195,888.
↓
Step 2 · Construction subtotal
Σ Q × Cs
TN: $240,722; PA: $291,788
↓
Step 3 · Mobilization
0.07 × construction
TN: $16,851; PA: $20,425
Spot check: 0.07 × $240,722 = $16,851.
↓
Step 4 · Contingency and escalation
Uses Eq. 3.7-4
(subtotal) × 1.20 × 1.031
TN: $257,573 × 1.236 = $318,360; PA: $312,213 × 1.236 = $385,895
Spot check: 1.20 × 1.03 = 1.236.
↓
Step 5 · Bounds
Repeat Steps 2-4 with every item at its low, then its high value
TN: $189,927 to $533,966; PA: $225,628 to $640,182
↓
Solution
About $318,000 in Tennessee and $386,000 in Pennsylvania; the PA job costs about 21% more.
Table 3.7-12. Example 3.7-2 line items, Tennessee and Pennsylvania
ItemQtyUnitUnit cost basisUnit costCost
Tennessee
Soldier pile and lagging wall face1,680SF$110 × 0.87$96$160,776
Undercut unsuitable toe soil600CYpublished TN price (2024)$11$6,330
Select granular backfill600CY$50 × 0.87$44$26,100
Separation geotextile900SY$2.50 × 0.87$2.17$1,957
Riprap at the ditch150CY$130 × 0.87$113$16,965
Underdrain behind the wall240LF$22 × 0.87$19$4,594
Railroad flagging20DAYnot location-adjusted$1,200$24,000
Pennsylvania
Soldier pile and lagging wall face1,680SF$110 × 1.06$117$195,888
Undercut unsuitable toe soil600CY$18 × 1.06$19$11,448
Select granular backfill600CY$50 × 1.06$53$31,800
Separation geotextile900SY$2.50 × 1.06$2.65$2,385
Riprap at the ditch150CY$130 × 1.06$138$20,670
Underdrain behind the wall240LF$22 × 1.06$23$5,597
Railroad flagging20DAYnot location-adjusted$1,200$24,000

Solution

Budget about $318,000 for the Tennessee site and $386,000 for the Pennsylvania site.

The wall is about 67% of the construction cost in both states, so the location factor on that one item drives most of the difference. Flagging is the same in both because the railroad sets the rate. Report the range ($190,000 to $534,000 in TN) with the typical figure until the wall is designed: pile size and embedment can move the wall unit cost by half in either direction. When the drilling and wall contractors quote, replace the database values with the quotes. The Estimate sheet of the Excel master is set up with these quantities and reproduces the PA total.

Open the state cost database and estimator → Download the Excel master
Pick a state, filter the items, enter quantities and get low, typical and high totals with mobilization, contingency and escalation, plus the same estimate in every state. The Excel master holds the same data with live formulas, so new state prices can be added as they are collected.

3.7.14.6 Keeping the database current

Treat the database as a living bid history. When a quote or bid comes in, add it to the State Prices sheet of the Excel master with its year and quantity, and it replaces national × F for that state. Escalate all values each year with the change in the NHCCI or the state's own cost index (Section 3.7.8). Review EST items against actual quotes at least once a year, and retire any published price older than about five years.

3.7.14.7 Sources

Unit costs are compiled from the public sources below; the summaries are in original wording. Individual railroads, clients, companies and projects are not named.

  • Arkansas Department of Transportation, Weighted Average Unit Prices, 1/15/2025 to 11/5/2025.Find source ↗
  • Tennessee Department of Transportation, Average Unit Prices, Awarded Contracts, January to December 2024.Find source ↗
  • West Virginia Division of Highways, Average Unit Bid Prices, 2025.Find source ↗
  • Oklahoma Department of Transportation, Weighted Average Item Price Report, January 2024 to June 2025.Find source ↗
  • Maine Department of Transportation, statewide geotechnical drilling bid tabulation, 2025.Find source ↗
  • Washington state drilling services contract price sheet, 2022; Minnesota Rules 2890.3100 and 2890.3300 (2022), maximum drilling costs.Find source ↗
  • A published CPT and DMT fee schedule, 2026; a county drilling fee schedule; a municipal average bid tabulation, 2025.Find source ↗
  • Geo-Institute, GeoTechTools technology cost pages: drilled and grouted soil nails; rock slope stabilization; prefabricated vertical drains.Find source ↗
  • Federal Highway Administration, National Highway Construction Cost Index (NHCCI).Find source ↗
  • Department of Defense, UFS 3-701-01, DoD Facilities Pricing Guide (2026), Table 4-1 area cost factors.Find source ↗