3.6.7 Access Effects on Cost and Schedule

Working out how crews and equipment will physically reach each boring, what has to be cleared or protected, and what that costs.
Author: Daniel P. Colwell
3.6.7 Access Effects on Cost and Schedule

Carry access in the estimate as its own items: clearing (by area and production), mats (by length and days), rut repair, extra mobilizations for separate setups, and the time the field engineer spends on the clearing day. Ask the driller or a clearing contractor to walk the optimized pathway with the reconnaissance report and price it against the estimate before notice to proceed.

Table 3.6-6. Access items in the estimate
ItemBasis
ClearingAcres of each cover type; mulcher production; hand cutting for trees over 4 in.
MatsLinear feet of soft ground and swale crossings; days on site
Rut repair and restorationAllowance per route on soft ground
MobilizationsOne per separate setup
Permits and right-of-entryPublic-way permit fees; time to obtain
Field engineerClearing-day oversight and re-flagging
Survey the ground at each boring when it is drilled. Lidar elevations used for access planning are for planning only.