Carry access in the estimate as its own items: clearing (by area and production), mats (by length and days), rut repair, extra mobilizations for separate setups, and the time the field engineer spends on the clearing day. Ask the driller or a clearing contractor to walk the optimized pathway with the reconnaissance report and price it against the estimate before notice to proceed.
| Item | Basis |
|---|---|
| Clearing | Acres of each cover type; mulcher production; hand cutting for trees over 4 in. |
| Mats | Linear feet of soft ground and swale crossings; days on site |
| Rut repair and restoration | Allowance per route on soft ground |
| Mobilizations | One per separate setup |
| Permits and right-of-entry | Public-way permit fees; time to obtain |
| Field engineer | Clearing-day oversight and re-flagging |