Quantify clearing from the flagged routes: a 12-ft lane along each route plus a 30 ft x 40 ft work pad at each off-road boring is a reasonable planning basis. Assign each segment the heaviest cover observed (wooded thicket, reed stand or open meadow) and count trees over 4 in., fallen trunks and ditch crossings. Then look for the shortest-effort network: the most direct parts of the flagged lines plus short new connectors.
| Item | Optimized pathway | Every flagged line |
|---|---|---|
| Clearing area | 1.06 ac (range 0.7 to 1.3) | 1.76 ac (range 1.2 to 2.1) |
| Trees over 4 in. | 6 | 16 |
| Fallen trunks to remove | 0 | 5 |
| Ditch crossings | 1 | 3 |
| Mulcher time in dense buckthorn (0.5 to 1.0 ac per day) | About 1 to 2 days for the 0.80 ac of thicket, plus half a day of hand cutting | Not estimated |
Range: low case a 10-ft lane on 80 percent of the pathway with smaller pads; high case a 14-ft lane with 40 ft x 40 ft pads.