3.6.5 Environmental Limits and Permits

Working out how crews and equipment will physically reach each boring, what has to be cleared or protected, and what that costs.
Author: Daniel P. Colwell
3.6.5 Environmental Limits and Permits
Table 3.6-5. Common environmental limits on access
LimitWhat to do
Mapped wetlandsKeep borings and lanes outside the wetland edge; confirm coverage under the nationwide permit for survey activities (Nationwide Permit 6) with the Corps of Engineers before mechanized clearing near a wetland
FloodplainNo permit expected for borings; fill or mats left in place may need one
Threatened and endangered speciesCheck the IPaC report; most railroad sites have listed species in the county but no critical habitat in the footprint
Migratory birdsClear outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them), or do a nest check first
Invasive speciesBuckthorn, bush honeysuckle and similar species are often listed as exotic weeds; clearing them is usually welcome, but do not spread cuttings off site
Impacted groundScreen cuttings; drum where readings or odors indicate; cross ditches on mats