Start every route at a public road, a yard road or a track-side drive, and record the length on road and the length off road. Off-road legs drive the cost.
| Boring | Access start | Road or drive (ft) | Off-road leg (ft) | Notes |
|---|---|---|---|---|
| AV-1 | Public road at a grade crossing | 189 | 362 | Shortest leg; drill first from this setup |
| AV-2 | Same | 189 | 1,063 | Crosses a box-culvert channel |
| AV-3 | Same | 189 | 1,412 | Crosses the same channel |
| AV-4 | Private drive south of the east reach | 0 | 1,820 | Longest leg; crosses the wet reach to get there |
| AV-5 | Same | 0 | 1,508 | Wetland-adjacent; mats likely |
Conceptual routes drawn on the project map before the reconnaissance; every route is verified on the driller's walk.
Overlay each route on county parcels. Where a lane leaves the railroad parcel, written right-of-entry is needed from that owner; where a boring itself plots outside the parcel (in one case 27 ft into public right-of-way), it needs either a public-way permit or relocation onto railroad property. Because phone GPS (about plus or minus 15 ft) and parcel lines are approximate, field-locate lanes inside the property line wherever possible.