01.4 Construction Methods.
  • Fill shall be placed in loose lifts not exceeding 8 in. (Type A) or 12 in. (Type B/C).
  • Each lift shall be compacted before the next lift is placed.
  • Fill moisture shall be conditioned to within ±2% of w_opt before compaction.
  • Subgrade shall be proof-rolled before the first fill lift is placed.
  • Each lift shall be compacted to the density required by the owner railroad's specification (commonly 95% of modified Proctor maximum dry density, ASTM D1557).
Types of Rollers
Types of Rollers
Project management · Twort and Rees (2004)

Watching Fill Quality and Allowing for Bulking

Twort and Rees make a practical point about earthwork control: in situ density tests prove compliance after the fact. A sand-cone test takes hours, so it records past performance and cannot serve as real-time control. Real-time control comes from an inspector who watches every load as it is dumped, spread and compacted, has authority to reject material, and calls the resident engineer when in doubt. The cues they describe:

  • Bounce. “Cushioning” or bounce under loaded haul trucks signals inadequate compaction, usually because the material is too wet or has too much clay or silt.
  • Rutting. Severe rutting means the material is too wet or too clayey.
  • Composition. Too much sand or gravel in a clay fill is easy to see. A change in clay color alone may not mean a change in suitability.
  • Early rejection. If unsuitable material is caught after only a few loads, it can usually be mixed out with suitable material. Deliberately blending two different fills seldom works; zone them separately instead and recheck borrow composition periodically.

On moisture, they note that wet borrow and a wet formation may simply mean stopping work. Rolling the day’s surface smooth and to a fall sheds rain. Dry fill must be watered on the spread layer and mixed in, not just wetted on the surface.

On quantities, they stress bulking. Haul units have a fixed body volume. At a bulking factor of 1.2, each load carries about 83% of its body volume measured in place; at 1.35 it carries only about 74%. A disposal price based on the first figure but met with the second is about 12% short. They quote typical bulking of about 1.1–1.3 for granular and soft soils, about 1.4 for hard clays and 1.6–1.7 for broken rock. They also show how excavator bucket size is matched to truck return interval and loading cycle time, after allowing for bulking.

For railroad work: On embankment widening and subgrade replacement during a work window, there is no time to wait for density results before the next lift or before returning the track to service. Write the inspector’s authority to stop placement and reject loads into this GSP. Specify a test fill or roller-pattern trial at the start, and use proof-rolling observations as the lift-by-lift control, with nuclear or sand-cone density tests as the record. Size haul and disposal by loose volume. Undercut ballast and fouled subgrade spoil bulks significantly, and disposal along the right-of-way or off site is often the item that runs over.

Source: Twort, A. C., and Rees, J. G. (2004). Civil Engineering Project Management, 4th ed. Oxford: Elsevier Butterworth-Heinemann, pp. 228–231. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Goldbloom (1989)

Measurement and Payment Provisions for Earthwork GSPs

Goldbloom treats Method of Measurement and Basis of Payment as the parts of an earthwork section that generate the most disputes. The quantity of earthwork is hard to predict, so most items are paid on measured actual quantities. A Fixed (Plan) quantity can be used where the geometry is fully defined. It is computed by average end areas from the engineer’s preconstruction cross sections and the plan dimensions, and it is marked “Fixed” in the bid schedule.

His recommended practices:

  • Excavation classes. Use Unclassified Excavation when little rock is expected. Use separate Common and Rock items when rock is present, and pay boulders larger than 1 CY as rock. The rock price includes scaling loose rock from the final faces.
  • Additional depth (undercut) excavation. Pay it separately per CY, measured in place before and after removal, and only where the engineer orders it. Pay the replacement backfill separately as well.
  • Temporary support. Pay trench sheeting separately by the square foot. If sheeting is buried in another unit price, the contractor has a financial reason to leave it out, which is a safety problem. If the contractor chooses to slope back instead, pay as if the trench were vertical and sheeted. Provide a separate item for sheeting the engineer orders left in place.
  • Borrow. Measure in the original position at the pit after clearing and stripping, not in the fill, because the placed fill may consolidate for years. If trucks must be used for measurement, require loads struck off level.
  • Dewatering is normally included in the related excavation price. Topsoil stripping is its own item.
  • Pay temporary fencing and barricades separately, so that the protection actually gets provided.
Backfilling and Trench Compaction
Backfilling and Trench Compaction

For railroad work: When adapting GSP-01 for subgrade rehabilitation or embankment repair, pay ordered undercut of unsuitable subgrade per CY, measured in place, with select fill and geosynthetics as separate items. Measure imported subballast and fill in place or at the source, not by truck count. If excavation support next to live track (shoring or soldier piles beside the fouling limit) is carried in a lump sum, its scope must be stated explicitly. Define the excavation classes so they match the boring logs. Whatever the specification says, the railroad’s contract form and pay-item list govern.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 208–218. Summarized and paraphrased. Full reference under Supplemental References.