GSP-01: EARTHWORK AND STRUCTURAL FILL

Reference templates and boilerplate specification language (Appendices A–C).
Authors: Daniel P. Colwell and Mario Ruel
GSP-01: EARTHWORK AND STRUCTURAL FILL

01.1 Scope. This section covers furnishing and placing all structural fill, embankment fill, and subgrade preparation within the limits shown on the contract drawings.

Earthwork provisions for railway embankments

Items from Profillidis that may be carried into project-specific special provisions for railway earthwork, subject to the engineer’s review:

Earthwork & Grading
Earthwork & Grading
  • Bench (step) the foundation where the existing ground slopes steeper than 1V:10H before placing fill.
  • Overbuild embankment width and height to allow for compaction of the fill after construction.
  • Compact the embankment body to 95% and any formation (top-of-subgrade) layer to 100% of Standard Proctor maximum dry density. Place the formation layer on subsoil at low moisture and keep it homogeneous, free of pockets of fine material.
  • Finish the top of subgrade with a 3–5% crossfall toward the drainage devices.
  • Where a separation geotextile is specified, place it under the subballast, never directly under ballast, and do not reduce the ballast or subballast thickness because of it.

After Profillidis (2014), §9.7.1, §9.12.2, §9.15.2. Full reference under Supplemental References.

Project management · Levy (2010)

Excavation Classification and Differing-Condition Thresholds in the Earthwork GSP

Writing for owners, Levy (2010) explains how the earthwork specification allocates subsurface risk. Declaring the site unclassified makes the contractor responsible for removing whatever is found, including rock, shale, hardpan, old foundations, pavement and debris, at the bid price. That protects the owner, but bidders respond by carrying a contingency large enough to cover the worst case, and the owner pays it whether or not bad ground appears. Levy asks owners to consider whether it is cheaper to pay actual costs for legitimate unforeseen conditions than to buy that contingency up front.

Earthworks — the Foundation of Every Project
Earthworks — the Foundation of Every Project

He summarizes two claim types recognized in public contracting and generally accepted privately. A Type I claim requires that the contract documents indicated the subsurface condition, that the contractor read them reasonably and relied on them in its estimate, that actual conditions were materially different and reasonably unforeseen, and that the costs claimed relate only to the difference. A Type II claim requires showing what usual conditions would have been expected, what was actually found, that it differed materially from the known or usual, and that cost increased. Owners typically answer that conditions were not really different, should have been anticipated, or that the contractor used the wrong equipment or inexperienced operators. Levy cites agencies that use a 15% quantity rule as evidence of material difference, and an FHWA statement that federal-aid contracts carry a changed-conditions clause triggered when a major item changes by more than 25%. To support a claim the contractor should record the time and condition observed, the superintendent’s daily-log entry, photographs, statements from the operator or foreman, and the operation and exact location, and should notify the owner’s representative before the material is removed.

Levy also cautions that springs absent during a summer drilling program may reappear in spring, and that rock can lie between widely spaced borings.

For railroad work: In GSP-01, state whether excavation is classified or unclassified, and if classified, define rock and unsuitable material by measurable criteria and pay limits (paylines) below subgrade. Where undercut of soft subgrade beneath track is expected, carry it as a unit-price item with an estimated quantity rather than burying it in a lump sum. Include a notification clause that requires the contractor to stop and notify the railroad’s representative and the geotechnical engineer of record before removing material it considers different, so the condition can be observed and photographed in place.

Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 21, 260–264. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Seeley (1993)

Measurement and Payment Rules for Earthwork Items

Seeley summarizes the earthwork rules of CESMM3 Class E. They are a useful checklist for writing the measurement-and-payment part of an earthwork special provision, because each rule closes off a common dispute:

  • One item, one excavation type, one material. Topsoil, rock, artificial hard material and “other natural material” are separate items. Disposal, on-site placement and reuse as fill are also separate items.
  • Depth class means total depth. The depth range in the description is the full depth of the excavation, not the thickness of each layer, because total depth is what drives the choice of equipment. Where rock about 10 ft thick lies under about 23 ft of gravel, Seeley measures two items. The first is excavation in other material, 16–33 ft maximum depth, ending at the top of rock. The second is excavation in rock, 6.6–16 ft maximum depth, starting at the top of rock.
  • Undefined material is soft natural soil. Running sand is not a separate class. It is treated as a groundwater problem, which is the contractor’s risk.
  • Isolated boulders and rock are not measured separately unless the piece exceeds about 1.3 CY, or about 0.33 CY where the excavation is less than about 6.6 ft wide.
  • Working space, support of excavation sides and removal of dead services are deemed included in the rate. Backfill to working space is not measured.
  • Net volumes from the drawings, with no allowance for bulking, shrinkage or waste. Disposal is the net excavation minus the net volume reused as fill. Double handling is paid only where it is expressly required.
  • Fill items include compaction. Fill items state the material and any differing compaction requirement. Trimming of excavated and filled slopes is measured separately by slope range.
  • A protective layer can be its own stage. The last 6–12 in. above formation can be made a separate item, and so can topsoil stripping.

For railroad work: for subgrade undercutting and embankment repair, the special provision should state the following. (1) The pay limits, as neat lines measured from a stated datum such as bottom of tie or design subgrade elevation. (2) A separate item for soft spots ordered below the planned undercut grade, so overruns are paid at a known rate. (3) A rock definition that uses the boring-log descriptions. (4) Whether fouled ballast is measured as excavation or as a separate removal-and-disposal item. (5) Whether stockpiling and rehandling is an item. Short track windows often force rehandling, so state it rather than leaving it to be argued.

Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 87–89. Summarized and paraphrased. Full reference under Supplemental References.