01.1 Scope. This section covers furnishing and placing all structural fill, embankment fill, and subgrade preparation within the limits shown on the contract drawings.
Items from Profillidis that may be carried into project-specific special provisions for railway earthwork, subject to the engineer’s review:
After Profillidis (2014), §9.7.1, §9.12.2, §9.15.2. Full reference under Supplemental References.
Writing for owners, Levy (2010) explains how the earthwork specification allocates subsurface risk. Declaring the site unclassified makes the contractor responsible for removing whatever is found, including rock, shale, hardpan, old foundations, pavement and debris, at the bid price. That protects the owner, but bidders respond by carrying a contingency large enough to cover the worst case, and the owner pays it whether or not bad ground appears. Levy asks owners to consider whether it is cheaper to pay actual costs for legitimate unforeseen conditions than to buy that contingency up front.
He summarizes two claim types recognized in public contracting and generally accepted privately. A Type I claim requires that the contract documents indicated the subsurface condition, that the contractor read them reasonably and relied on them in its estimate, that actual conditions were materially different and reasonably unforeseen, and that the costs claimed relate only to the difference. A Type II claim requires showing what usual conditions would have been expected, what was actually found, that it differed materially from the known or usual, and that cost increased. Owners typically answer that conditions were not really different, should have been anticipated, or that the contractor used the wrong equipment or inexperienced operators. Levy cites agencies that use a 15% quantity rule as evidence of material difference, and an FHWA statement that federal-aid contracts carry a changed-conditions clause triggered when a major item changes by more than 25%. To support a claim the contractor should record the time and condition observed, the superintendent’s daily-log entry, photographs, statements from the operator or foreman, and the operation and exact location, and should notify the owner’s representative before the material is removed.
Levy also cautions that springs absent during a summer drilling program may reappear in spring, and that rock can lie between widely spaced borings.
For railroad work: In GSP-01, state whether excavation is classified or unclassified, and if classified, define rock and unsuitable material by measurable criteria and pay limits (paylines) below subgrade. Where undercut of soft subgrade beneath track is expected, carry it as a unit-price item with an estimated quantity rather than burying it in a lump sum. Include a notification clause that requires the contractor to stop and notify the railroad’s representative and the geotechnical engineer of record before removing material it considers different, so the condition can be observed and photographed in place.
Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 21, 260–264. Summarized and paraphrased. Full reference under Supplemental References.
Seeley summarizes the earthwork rules of CESMM3 Class E. They are a useful checklist for writing the measurement-and-payment part of an earthwork special provision, because each rule closes off a common dispute:
For railroad work: for subgrade undercutting and embankment repair, the special provision should state the following. (1) The pay limits, as neat lines measured from a stated datum such as bottom of tie or design subgrade elevation. (2) A separate item for soft spots ordered below the planned undercut grade, so overruns are paid at a known rate. (3) A rock definition that uses the boring-log descriptions. (4) Whether fouled ballast is measured as excavation or as a separate removal-and-disposal item. (5) Whether stockpiling and rehandling is an item. Short track windows often force rehandling, so state it rather than leaving it to be argued.
Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 87–89. Summarized and paraphrased. Full reference under Supplemental References.