APPENDIX C — GEOTECHNICAL SPECIAL PROVISIONS (GSP) TEMPLATE

Reference templates and boilerplate specification language (Appendices A–C).
Authors: Daniel P. Colwell and Mario Ruel
APPENDIX C — GEOTECHNICAL SPECIAL PROVISIONS (GSP) TEMPLATE

No additional content.

Project management · Twort and Rees (2004)

Measurement and Payment Pitfalls for Geotechnical Pay Items

Twort and Rees’ chapter on bills of quantities is essentially a list of the measurement-and-payment wording that leads to claims. The points that bear on geotechnical work:

  • Quantities are a best estimate. Do not pad them, and do not shift quantities between depth bands to build in a hidden reserve. Some owners pay the bid quantity unless the variation is obvious, so the quantities must be fair to both parties.
  • Rock. Where rock is suspected but its extent is unknown, a provisional quantity is hard to bid. The authors suggest a provisional sum with a rate negotiated if rock is found, while expecting a related delay claim. Define rock in the contract by the method needed to remove it: explosives or hydraulic or pneumatic breakers. Consider a separate intermediate class for hard bands that need ripping but are not rock. Measure rock jointly in the open excavation with the contractor’s staff.
  • Data to bidders. Supply the geophysical and boring data so that bidders can make their own judgment of rock depth and extent.
  • Working space. State that only the volume within the pay limits is measured, and repeat this in items where contractors commonly claim extra excavation.
  • Earthwork from borrow. Fill is paid as net volume in place. Give bidders all available data on the fill source, its bulking and its unit weight. Make the filling rate include setting aside and double-handling unsuitable borrow material, which cannot be measured. Use separate items for stripping overburden and for reinstating the borrow pit.
  • Method-related and temporary works items. If temporary works such as access roads or dewatering are itemized as owner requirements, they must be fully specified. Otherwise leave them for the bidder to price as method-related items, fixed or time-related, and state that listing a method does not imply the engineer has approved it.

For railroad work: Each GSP in this template should end with a measurement-and-payment paragraph that applies these lessons:

  • Undercut paid by the cubic yard within neat lines below the plan subgrade, with a stated pay limit.
  • Unsuitable subgrade removal and replacement as a separate unit-price item with an estimated quantity tied to the borings.
  • Rock defined by removal method.
  • Geotextile and drainage pipe paid by area and length.
  • Temporary shoring adjacent to live track, and dewatering, either fully specified as owner items or left as contractor-designed lump sums, but not both.

Spell out which item absorbs the work of handling material during short track windows, such as stockpiling and re-handling, so that it does not become an extra.

Source: Twort, A. C., and Rees, J. G. (2004). Civil Engineering Project Management, 4th ed. Oxford: Elsevier Butterworth-Heinemann, pp. 182–186, 189–194. Summarized and paraphrased. Full reference under Supplemental References.

Project management · ASCE (2013)

Writing Enforceable GSP Language: Common Defects and a Review Checklist

The ASCE guide lists recurring specification defects drawn from Committee surveys:

  • conflicts between sections or with the drawings;
  • unattainable results or tolerances, which make users lose confidence in the whole document;
  • ambiguous intent, which produces high bid contingencies and arguments during construction;
  • references to standards that are unnecessary or not available in the field;
  • over-specification of methods.

Its writing rules:

  • Use short sentences in the imperative mood (“Compact each lift…”).
  • Use “shall” for the contractor and “will” for the owner or engineer, and do not interchange them.
  • Define “day” (calendar, working, or 24-hour).
  • Drop “any” and “all” when the context already covers them.
  • Remove phrases such as “as the engineer shall direct”.

Appendix F of the guide classifies actual problem wording:

  • Superfluous: “furnish all labor, supervision, tools…” belongs in the conditions of the contract, not in every technical section.
  • Ambiguous: “shall not occur without written approval” without saying whose approval. Another example is “an additional set for each additional 100 cubic yards”, which leaves open whether 199 CY needs one set or two.
  • Left to the discretion of site personnel: “no further lifts until the inspector allows”, “compaction tests at locations selected by the Owner”, “restore to original condition as much as possible”, “neat and workmanlike manner”. The guide notes that bidders price the worst case and then perform to a reasonable one. It recommends replacing each phrase with a method, a code reference, or a measurable criterion.
  • Conflicts with commercial terms: safety, rejection rights and schedule statements already covered in the general conditions.

The Appendix G checklist is a quick review tool. It asks whether related sections are listed and duplication removed; whether references are current, available in the field and have their options selected; who tests, by what method and in what report format; and who measures, by what method, and whether payment is tied to the measured quantity.

For railroad work: GSP drafts should be checked against Appendix F before issue. For example, “Compaction tests shall be taken at locations selected by the Engineer” can be rewritten as “The Engineer will test in-place density at a minimum frequency of one test per [__] CY per lift, at locations selected by stratified random sampling”, with the frequency taken from the railroad’s standard. “Remove unsuitable material as directed” should become a defined criterion, such as a proof-roll deflection or classification trigger, plus an ordered-quantity pay item. Phrases such as “protect the track” should be replaced by citing the railroad’s fouling, flagging and monitoring requirements.

Source: ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers, pp. 3–4, 31–33, 54–60. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Seeley (1993)

Fixed, Time-Related and Quantity Items in the Bid Schedule

Seeley describes the method-related charges introduced in CESMM. Many construction costs do not scale with the quantity of permanent work. Examples are bringing plant to site and removing it, site offices, temporary works and supervision. If these costs are spread through unit rates, any change in quantity overpays or underpays the contractor, and disputes follow. CESMM lets the bidder enter them separately, as one of two types:

  • Fixed charges. These do not depend on quantity or time, for example establishing and removing a plant. They are paid when the operation described is complete.
  • Time-related charges. These run in proportion to how long the resource is needed, for example running costs or maintaining a temporary access road. They are paid in instalments according to the proportion of the activity’s duration that has elapsed or been completed.

Method-related charges are not remeasured. If the contractor priced a crane for 22 weeks and used it for 28, the price does not change automatically. If dewatering priced in the bid turns out to be unnecessary in a dry season, the sum is still paid, because the contractor carried the risk. The charges are adjusted only when an ordered variation changes the work or its duration. The contractor must describe each charge, including the resources and the parts of the work it relates to, but is not bound to use the method described. Seeley notes the risks: front-loaded charges, and vague descriptions that are hard to certify.

For railroad work: on railroad jobs, durations depend on track windows, and the windows are controlled by train traffic and the railroad’s operating decisions. A geotechnical special provision template therefore benefits from three kinds of item:

  1. Fixed items, such as mobilizing hi-rail or on-track equipment, building a temporary access road or crossing, and installing and removing instrumentation.
  2. Time-related items, paid per day or per window, such as dewatering, standby while waiting for track time, and an instrument-reading program.
  3. Quantity items, such as cubic yards of undercut, tons of subballast and ballast, and linear feet of drains.

When a cancelled window then stretches the schedule, the extra cost lands on the time-related items, where it can be checked. It is not hidden in the cubic-yard rate. The template should also state which costs the railroad pays directly, such as flagging and work trains, so that bidders do not price them twice.

Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 59–66. Summarized and paraphrased. Full reference under Supplemental References.