8.3.6 Example: Project Update Memo

Short technical documents: when to write a memorandum instead of a report, how to structure it, and the review it needs before it goes out.
Author: Daniel P. Colwell
8.3.6 Example: Project Update Memo

The outline below is condensed from a project update memo on a siding re-grade, with client details removed.

Table 8.3-5. Example project update memo (condensed)
PartContent
SummaryA design check found that the west reach had embankment work but no planned borings. Three borings were added and all borings renumbered west to east, giving 10 borings and 132 ft of drilling. The drilling RFP was revised and the estimate updated.
FindingThe only nearby boring was a 4-ft hand auger on the other side of the track, in topsoil only; a creek and box culvert nearby suggest soft alluvium under the fill; the reach is about 2.7 miles from the others and needs a separate setup.
DetailsBoring table: ID, reach, station, offset, depth, coring, coordinates, previous ID.
Changes (RFP Revision 2)Reach added to site reference and access; borings renumbered; totals 10 borings, 132 ft, 15-ft coring contingency, up to 16 Shelby tubes; laboratory quantities updated.
Cost effectSubconsultant rates are placeholders (previous invoice plus 20 percent) until the quote is received.
Files updatedRFP, map files, figures, project pages and cost workbook; superseded files moved out.
Open itemsConfirm the new boring locations with the geotechnical lead; draw the access route; replace placeholder rates when the quote arrives.