The outline below is condensed from a project update memo on a siding re-grade, with client details removed.
| Part | Content |
|---|---|
| Summary | A design check found that the west reach had embankment work but no planned borings. Three borings were added and all borings renumbered west to east, giving 10 borings and 132 ft of drilling. The drilling RFP was revised and the estimate updated. |
| Finding | The only nearby boring was a 4-ft hand auger on the other side of the track, in topsoil only; a creek and box culvert nearby suggest soft alluvium under the fill; the reach is about 2.7 miles from the others and needs a separate setup. |
| Details | Boring table: ID, reach, station, offset, depth, coring, coordinates, previous ID. |
| Changes (RFP Revision 2) | Reach added to site reference and access; borings renumbered; totals 10 borings, 132 ft, 15-ft coring contingency, up to 16 Shelby tubes; laboratory quantities updated. |
| Cost effect | Subconsultant rates are placeholders (previous invoice plus 20 percent) until the quote is received. |
| Files updated | RFP, map files, figures, project pages and cost workbook; superseded files moved out. |
| Open items | Confirm the new boring locations with the geotechnical lead; draw the access route; replace placeholder rates when the quote arrives. |