Railway Ground Hazard Risk Management · 5.0 · Testing
Sections · open a dropdown to go to a section or subsection

5.4.6 Worked Example

What contaminants to expect in railroad ground, how to sample for them during a geotechnical program, and how to manage drilling waste and spoil.
Author: Daniel P. Colwell
5.4.6 Worked Example
The example uses a generic site and is not taken from any client project. It follows the five-part format.
Example 5.4-1: Drums of Drilling Waste for a Yard Investigation

Twenty borings, each 30 ft deep, are planned with hollow-stem augers in a rail yard with a history of fueling. The owner requires all cuttings to be drummed and characterized before disposal.

Given

VariableValueDescription
n20Number of borings
L30 ftDepth of each boring
D8 in. (0.667 ft)Outside diameter of the auger flights (hole diameter)
fb1.25Bulking factor for cuttings
Drum55 gal = 7.35 cf, filled to 80%Usable volume 5.88 cf per drum

Required

  • Volume of cuttings
  • Number of drums to carry in the estimate

Equations

  1. Eq. 5.4-1: Vc = (πD2/4) L n fb — cuttings volume
  2. Eq. 5.4-2: N = Vc / (7.35 × 0.8) — drums

Steps

Step 1 · Hole area
π (0.667)2 / 4
A = 0.349 sq ft
Spot check: An 8-in. circle is about a third of a square foot.
↓
Step 2 · In-place volume
0.349 × 30 ft × 20 borings
209 cf
Spot check: About 10.5 cf per boring.
↓
Step 3 · Bulked volume
209 × 1.25
Vc ≈ 262 cf
↓
Step 4 · Drums
262 / (7.35 × 0.8) = 262 / 5.88
44.5, use 45 drums
Spot check: About 2.2 drums per boring; at roughly 2 drums per 30-ft boring this is reasonable.
↓
Solution
The borings will produce about 262 cf of bulked cuttings, requiring about 45 drums for cuttings alone, before decontamination water.

Solution

The borings will produce about 262 cf of bulked cuttings, requiring about 45 drums for cuttings alone, before decontamination water.

Carry about 50 drums in the estimate to cover decontamination water and the partly filled last drum at each location, plus one composite characterization sample per group of drums as the receiving facility requires. The drums also need a staging area on railroad property that is clear of tracks and accessible to the disposal contractor; include that in the access and right-of-entry planning.

If the yard history suggests petroleum only, ask the client whether cuttings from borings with clean PID readings can be spread on site. That decision can cut the drum count sharply, but it belongs to the client and its environmental staff, not to the drilling crew.